Execution
Tuas Phase 2 advances from marine works toward terminal handover
MPA now puts Tuas Port Phase 2 reclamation at 79.5% as of December 2025. Its annual report said the first six completed berths were targeted for handover to PSA in March 2026, but it does not confirm that the handover occurred. Marine-civil acceptance, terminal readiness and berth commissioning remain separate gates.
What changed
MPA's programme timeline dates Phase 2 reclamation commencement to 7 March 2018, while Penta-Ocean's 1 March award record and MPA's 25 April agreement record define the Penta-Ocean-Hyundai-Boskalis joint venture and a package covering 387 hectares, dredging, soil improvement, caissons, wharf, and 9.1 kilometres of wall. The first caisson was installed on 4 July 2019 and all caisson fabrication was completed in April 2022. Owner factsheets advanced the aggregate reclamation record from about 60% in March 2023 to 70% in March 2024 and 75% by December 2024. MPA's 2024 annual report adds that all 227 caissons were constructed and 185 installed. The 2025 annual report moves reclamation to 79.5% as of December 2025 and says MPA was on track to hand the first six completed berths to PSA in March 2026; it does not say that handover occurred. Port Marine Notices 43 and 73 of 2026 confirm continuing work-zone and bulk-carrier controls through September and December 2026. The 8.6-kilometre wharf and 9.1-kilometre seawall figures are different measures. These sources do not establish final installation, completed dredging, marine acceptance, terminal-system readiness, named Phase 2 berth commissioning, or capacity in service.
Why it matters
A reclamation percentage or caisson milestone can look like terminal completion while residual seawall, dredging, wharf acceptance, utilities, equipment, systems integration, navigation controls, and commissioning still determine when a berth can enter reliable service. Owners, contractors, suppliers, and operators need the gates reported separately to understand remaining work and capacity timing.
Decision read
What remains open
The 79.5% measure adds a later civil-progress point, but it does not close the delivery chain. The immediate evidence gap is whether the six-berth March 2026 handover actually happened and what land, wharf, utilities and acceptance scope it covered. Phase 2 still has to move through marine-civil close-out, PSA terminal construction and systems integration, berth testing, commissioning and capacity ramp-up. Tuas Port's operating Phase 1 berths cannot be attributed to Phase 2.
Next watchpoints
- Final caisson, seawall, reclamation, and marine-civil acceptance
- Dredged access, berth geometry, navigation controls, and residual marine work zones
- Additional MPA-to-PSA land and wharf handovers tied to named berths
- Terminal utilities, cranes, yard systems, automation, and integration testing
- Berth commissioning, first commercial calls, and capacity entering service
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 12
- Port of the Future: Tuas Port Maritime and Port Authority of Singapore, Publication date not stated; evidence reviewed 20 July 2026
- Development of Tuas Next Generation Port Phase 2 begins Maritime and Port Authority of Singapore, 4 July 2019
- MPA Annual Report 2024: Tuas Port development progress Maritime and Port Authority of Singapore, 2025
- MPA Annual Report 2025: Tuas Port development progress Maritime and Port Authority of Singapore, 2026; progress measured December 2025
- MPA signs the SGD 1.46 billion Tuas Terminal Phase 2 agreement Maritime and Port Authority of Singapore, 25 April 2018
- MPA reports Phase 2 reclamation about 60% complete Maritime and Port Authority of Singapore, 3 March 2023
- MPA reports Phase 2 reclamation about 70% complete Maritime and Port Authority of Singapore, 5 March 2024
- MPA reports Phase 2 reclamation about 75% complete Maritime and Port Authority of Singapore, 15 January 2025
- Port Marine Notice No. 43 of 2026: work at Tuas Terminal Phase 2 Maritime and Port Authority of Singapore, 18 March 2026
- Port Marine Notice No. 73 of 2026: bulk-carrier operations at Tuas Terminal Phase 2 Maritime and Port Authority of Singapore, 19 May 2026
- Tuas Terminal Phase 2 reclamation, wharf, and dredging award Penta-Ocean Construction, 1 March 2018
- PSA Singapore terminal profile PSA International, Publication date not stated; evidence reviewed 20 July 2026
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.
Review methodology Open intelligence archive Submit a correction