Tuas Phase 2 advances from marine works toward terminal handover

Published 14 July 2026 Updated 20 July 2026 Editorial responsibility IMWO Region Asia Pacific Confidence Confirmed
First Tuas Port Phase 2 caisson afloat beside the Hyundai E&C HFD 20000 marine construction vessel and an assisting tug

Maritime and Port Authority of Singapore

MPA now puts Tuas Port Phase 2 reclamation at 79.5% as of December 2025. Its annual report said the first six completed berths were targeted for handover to PSA in March 2026, but it does not confirm that the handover occurred. Marine-civil acceptance, terminal readiness and berth commissioning remain separate gates.

What changed

MPA's programme timeline dates Phase 2 reclamation commencement to 7 March 2018, while Penta-Ocean's 1 March award record and MPA's 25 April agreement record define the Penta-Ocean-Hyundai-Boskalis joint venture and a package covering 387 hectares, dredging, soil improvement, caissons, wharf, and 9.1 kilometres of wall. The first caisson was installed on 4 July 2019 and all caisson fabrication was completed in April 2022. Owner factsheets advanced the aggregate reclamation record from about 60% in March 2023 to 70% in March 2024 and 75% by December 2024. MPA's 2024 annual report adds that all 227 caissons were constructed and 185 installed. The 2025 annual report moves reclamation to 79.5% as of December 2025 and says MPA was on track to hand the first six completed berths to PSA in March 2026; it does not say that handover occurred. Port Marine Notices 43 and 73 of 2026 confirm continuing work-zone and bulk-carrier controls through September and December 2026. The 8.6-kilometre wharf and 9.1-kilometre seawall figures are different measures. These sources do not establish final installation, completed dredging, marine acceptance, terminal-system readiness, named Phase 2 berth commissioning, or capacity in service.

Why it matters

A reclamation percentage or caisson milestone can look like terminal completion while residual seawall, dredging, wharf acceptance, utilities, equipment, systems integration, navigation controls, and commissioning still determine when a berth can enter reliable service. Owners, contractors, suppliers, and operators need the gates reported separately to understand remaining work and capacity timing.

Decision read

What remains open

The 79.5% measure adds a later civil-progress point, but it does not close the delivery chain. The immediate evidence gap is whether the six-berth March 2026 handover actually happened and what land, wharf, utilities and acceptance scope it covered. Phase 2 still has to move through marine-civil close-out, PSA terminal construction and systems integration, berth testing, commissioning and capacity ramp-up. Tuas Port's operating Phase 1 berths cannot be attributed to Phase 2.

Next watchpoints

  • Final caisson, seawall, reclamation, and marine-civil acceptance
  • Dredged access, berth geometry, navigation controls, and residual marine work zones
  • Additional MPA-to-PSA land and wharf handovers tied to named berths
  • Terminal utilities, cranes, yard systems, automation, and integration testing
  • Berth commissioning, first commercial calls, and capacity entering service

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.