Port of Ploce Authority developed the marine infrastructure while Luka Ploce d.d. took the equipment and operating concession. A CYES-Viadukt joint venture received the HRK 406.49 million civil contract; TEC Inc. and BCEOM with Hidroprojekt designed the terminal, and Institut IGH with Invest Inzenjering supervised construction. CNBM International Engineering supplied and installed the cargo-handling system, supported by named Croatian specialists. The civil platform finished in 2016, but equipment delivery, installation, testing and regular service extended the operating chain to February 2021.
Project signal
Completed in Croatia
Current statusCivil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacitySource confidenceConfirmed
Location
Croatia / Europe
Segment
Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems
Status
Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity / Confirmed
Last checked
2 August 2026
Coverage
Related sectors
Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Port of Ploce Authority as public infrastructure owner and Luka Ploce d.d. as equipment investor, terminal concessionaire and operator
Delivery parties
CYES (Construcciones y Estudios) and Viadukt - joint venture for the first-phase terminal infrastructure, TEC Inc. and BCEOM with Hidroprojekt - concept and main-design consortium, Institut IGH and Invest Inzenjering - construction-supervision joint venture, Keller Geotechnik - accelerated consolidation of the terminal stockyard completed in 2008, Rijeka Projekt - independent design review, Exstructa - infrastructure project-management and technical-support services, CNBM International Engineering Co. Ltd. - main contractor for manufacture, delivery, installation and integration of terminal handling equipment, IVICOM Consulting and Iskraemeco - named equipment-package subcontractors in HELB's project record, HELB - conveyor and transfer-station installation, testing and commissioning subcontractor
Contract route
The World Bank procedure separated public basic infrastructure from concessionaire equipment. Port of Ploce Authority signed the HRK 406,492,091 civil contract with the CYES-Viadukt joint venture in March 2012 and the supervision contract with Institut IGH-Invest Inzenjering. Luka Ploce later signed CNBM International Engineering for manufacture and installation of the handling system under the public-private delivery split. HELB identifies IVICOM Consulting, Iskraemeco and HELB as downstream equipment-package subcontractors.
Execution window
Design appointments began in 2007, ground consolidation finished in 2008, and principal civil works ran from April 2012 to June 2016 after multiple extensions. CNBM equipment was delivered on 23 October 2017; HELB records installation, testing and commissioning work beginning in April 2018. Trial operation started on 1 March 2019. The 19 February 2021 Orient Cavalier call marked the start of regular terminal operation. Luka Ploce's 2024 sustainability report continues to describe the terminal as operating and records EUR 36.93 million invested in equipment and new cranes.
Works package
Create the Vlaška-channel bulk terminal on an approximately 240,000 m2 site, with an open reinforced-concrete berth structure, access bridge, stockyard, rail interfaces and utilities; install a grab ship unloader, mobile crane, enclosed conveyor and transfer-station system, stacker-reclaimer and rail-wagon loading station. The operator states a 365-metre pier, nominal 18-metre draft, 4.6 million t/y first-phase capacity and potential expansion to 6.2 million t/y. Its current port card limits normal ship particulars to 300 m LOA, 46 m beam and 17.5 m draft, or 17.8 m at high tide.
Marine interfaces
The berth, approach and reclaimed stockyard had to align deep-draft bulk-carrier access with an open piled quay, seismic design, soil consolidation, rail logistics and the concessionaire's later equipment geometry. Audit records show the design changed repeatedly, including quay length and access-channel excavation assumptions. The current operator page supports Cape-size handling capability; published records do not disclose a final dredging quantity or an as-built hydrographic acceptance record.
Commercial evidence boundary
The HRK 406.49 million, approximately EUR 54.12 million, amount is the civil-works contract. Luka Ploce's 2024 sustainability report records EUR 36.93 million invested in equipment and new cranes. The roughly EUR 200 million figure belongs to the wider Trade and Transport Integration programme, not this terminal alone. EBRD signed a EUR 11.2 million loan in 2007, but the Port Authority's audit says only EUR 393,144 of interest and fees was drawn before the facility was repaid from its own funds in 2012; the World Bank review records the co-financing as cancelled.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Operator documented the terminal as an operating sustainability asset
Luka Ploce's 2024 sustainability report records commencement of DBCT operations, EUR 36.93 million of equipment and crane investment, and later electrification work, providing a current operating-era source beyond the original project page.
Regular operation began with the Orient Cavalier call
Croatian public broadcaster HRT reported that the 110,000-tonne coal cargo marked regular service, roughly five years after civil completion and two years after trial operation began.
Civil infrastructure completed without operating equipment
World Bank evaluation records physical completion in June 2016 while the terminal remained non-operational because the concessionaire's equipment was still pending.
Luka Ploce contracted CNBM for the handling system
The concessionaire selected CNBM International Engineering to manufacture and install equipment under the public-private package split before the later installation and commissioning programme.