Location
Croatia / Europe
Project record
Civil infrastructure was completed in June 2016, CNBM equipment arrived in October 2017, trial operation began in March 2019 and regular vessel service began in February 2021. The operator's current port card lists a 2,000 t/h grab ship unloader and 4.6 Mt/y design capacity
Port of Ploce Authority developed the marine infrastructure while Luka Ploce d.d. took the equipment and operating concession. A CYES-Viadukt joint venture received the HRK 406.49 million civil contract; TEC Inc. and BCEOM with Hidroprojekt designed the terminal, and Institut IGH with Invest Inzenjering supervised construction. CNBM International Engineering supplied and installed the cargo-handling system, supported by named Croatian specialists. The civil platform finished in 2016, but equipment delivery, installation, testing and regular service extended the operating chain to February 2021.
Luka Ploce d.d.; exact operating terminal and 2,000 t/h ship unloader
Croatia / Europe
Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems
Completed / Confirmed
2 August 2026
Coverage
Deep-draft dry-bulk terminal, open piled quay, ground improvement, conveyors and rail-loading systems is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogLuka Ploce's 2024 sustainability report records commencement of DBCT operations, EUR 36.93 million of equipment and crane investment, and later electrification work, providing a current operating-era source beyond the original project page.
SourceCroatian public broadcaster HRT reported that the 110,000-tonne coal cargo marked regular service, roughly five years after civil completion and two years after trial operation began.
SourceTrial running provided the first system-level evidence after equipment installation, but it did not establish regular commercial service.
SourceThe operator confirmed delivery of the Chinese-built handling system while installation, testing and terminal integration still remained ahead.
SourceWorld Bank evaluation records physical completion in June 2016 while the terminal remained non-operational because the concessionaire's equipment was still pending.
SourceThe concessionaire selected CNBM International Engineering to manufacture and install equipment under the public-private package split before the later installation and commissioning programme.
SourceThe HRK 406 million infrastructure award established the principal marine-civil joint venture and an original 26-month construction period.
SourceEvidence gap