Skandia Gateway combines an active 700-metre quay reinforcement and deepening package, an awarded Boskalis port-side blasting and dredging contract, and a re-procured Swedish Maritime Administration fairway package. The former joint dredging procurement was cancelled in October 2025 after bids exceeded the state budget, then split and redesigned. The optimized authority design keeps 16.5 metres as the fairway depth with 17.5 metres as an option and reduces dredged areas without publishing a replacement total volume. Usable capacity still depends on accepted quay, port reach, national fairway, navigation aids, and operating controls.
Sweden / Europe
Port infrastructure
Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The Swedish Maritime Administration reduced selected fairway and turning-area dredging, retained 16.5 metres as the base depth with 17.5 metres as an option, and separated the port-side and national contracts. The update advances procurement but does not establish the revised total volume, national award, completed geometry, or operating draft.
Read controlling sourceThe approximately SEK 202 million contract covers blasting and dredging beside the terminal quay during an October 2026 to March 2027 window. The port-side package is separate from the national fairway award; mobilisation, accepted port-reach depth and usable vessel draft remain future evidence.
Read controlling sourceThe signed approximately SEK 850 million financing supports a roughly 700-metre quay project with an estimated SEK 1.7 billion cost. It does not finance or award the complete national fairway, prove construction completion, or establish operating capacity.
Read controlling sourceThe two public owners stopped the combined tender because bids exceeded the state-funded budget and announced a split into quay-adjacent and wider-fairway packages. The cancellation invalidated the former procurement route and schedule as an award baseline.
Read controlling sourceThe tender described about 9 million cubic metres, 12 beacons, an August 2026 planned start, and February 2028 target completion. Those figures document the former tender frame; the later cancellation and redesign mean they are not the current contracted quantity or schedule.
Read controlling sourceThe just-over-SEK-1-billion partnering order moved the quay from detailed design into construction, covering front sheet piling, foundation piles, a crane girder and utility systems. The notice leaves completion and the separate fairway award unresolved.
Read controlling sourceDelivery watch
Track Boskalis mobilisation for the October 2026 window, NCC quay and crane-beam progress, dredged-material and turbidity controls, port-reach survey acceptance, the national fairway contract targeted for early 2027, the revised controlled dredging quantity, August 2027 authority mobilisation, edge-beacon changes, hydrographic acceptance, and formal publication of usable draft after system commissioning.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerNCC's 7 December 2023 release controls the construction-stage order and immediate transition from design into production. The Port of Gothenburg's current project page records February 2024 quay reinforcement, Q3 2027 authority dredging, and programme completion during 2029. The Swedish Maritime Administration controls the 22 November 2024 joint procurement, its 17 October 2025 cancellation after over-budget bids, and the 4 May 2026 optimized split. That latest authority release sets a 16.5-metre base depth, a 17.5-metre option, reduced dredged areas, a target national contract in early 2027, August 2027 dredging, and end-2028 completion; it does not publish a revised total volume. The port's 20 April 2026 release controls the approximately SEK 202 million Boskalis port-side package and October 2026 to March 2027 window. EIB's signed record controls the roughly 700-metre quay package, estimated SEK 1.7 billion cost, approximately SEK 850 million finance, and environmental controls. The closed CEF study is preparatory evidence, not construction proof. The port's 11-million-cubic-metre overview, the former tender's 9-million-cubic-metre frame and the 2028/2029 completion statements remain unreconciled without a newer common baseline.
Phase: construction. Evidence reviewed: 15 July 2026.