Location
Sweden / Europe
Project record
Skandia Gateway combines an active 700-metre quay reinforcement and deepening package, an awarded Boskalis port-side blasting and dredging contract, and a re-procured Swedish Maritime Administration fairway package. The former joint dredging procurement was cancelled in October 2025 after bids exceeded the state budget, then split and redesigned. The optimized authority design keeps 16.5 metres as the fairway depth with 17.5 metres as an option and reduces dredged areas without publishing a replacement total volume. Usable capacity still depends on accepted quay, port reach, national fairway, navigation aids, and operating controls.
Sweden / Europe
Port infrastructure
Quay construction active; port-side dredging awarded; optimized national fairway package in procurement for 2027-2028 delivery / Confirmed
15 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe Swedish Maritime Administration reduced selected fairway and turning-area dredging, retained 16.5 metres as the base depth with 17.5 metres as an option, and separated the port-side and national contracts. The update advances procurement but does not establish the revised total volume, national award, completed geometry, or operating draft.
SourceThe approximately SEK 202 million contract covers blasting and dredging beside the terminal quay during an October 2026 to March 2027 window. The port-side package is separate from the national fairway award; mobilisation, accepted port-reach depth and usable vessel draft remain future evidence.
SourceThe signed approximately SEK 850 million financing supports a roughly 700-metre quay project with an estimated SEK 1.7 billion cost. It does not finance or award the complete national fairway, prove construction completion, or establish operating capacity.
SourceThe two public owners stopped the combined tender because bids exceeded the state-funded budget and announced a split into quay-adjacent and wider-fairway packages. The cancellation invalidated the former procurement route and schedule as an award baseline.
SourceThe tender described about 9 million cubic metres, 12 beacons, an August 2026 planned start, and February 2028 target completion. Those figures document the former tender frame; the later cancellation and redesign mean they are not the current contracted quantity or schedule.
SourceThe just-over-SEK-1-billion partnering order moved the quay from detailed design into construction, covering front sheet piling, foundation piles, a crane girder and utility systems. The notice leaves completion and the separate fairway award unresolved.
SourceEvidence gap