Chennai Port Berth 19A North Quay reconstruction

Aerial view across Chennai Port's inner docks, working quays, cargo yards and harbor entrance

Saiphani02 via Wikimedia Commons, CC BY-SA 4.0; whole-port context photographed 11 February 2025, not Berth 19A construction evidence

Chennai Port Authority has commissioned IIT Madras to audit Berth 19A at North Quay and prepare detailed engineering for a new structure. IIT Madras records project IC24251239CPCPTXNTPHOC with a 30 December 2024 start, 31 December 2027 close and INR 5.074 million sanctioned value. Official records identify the existing 198-metre berth at a scheduled depth of 8.5 metres; a construction package, contractor and notice to proceed have not been published.

Project signal

Design in India

Current status Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified Source confidence Confirmed

Location

India / Asia Pacific

Segment

Port infrastructure

Status

Technical audit and detailed engineering are commissioned through 31 December 2027; no construction tender, award or works contractor is verified / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Chennai Port Authority
Delivery parties
Indian Institute of Technology Madras - technical audit and detailed-engineering consultant; principal investigator Murali K, Construction contractor - no tender or award verified by 1 August 2026
Contract route
IIT Madras lists the owner-side consultancy as project IC24251239CPCPTXNTPHOC. The consultancy selection method and downstream construction procurement are not disclosed. A Chennai Port Authority tender or contract record must establish any future works route, bidder list and award.
Execution window
The IIT Madras assignment runs from 30 December 2024 to 31 December 2027. That close date belongs to the consultancy ledger and is not evidence of a construction completion date.
Works package
Technical audit of Berth 19A at North Quay and detailed engineering for construction of a new berth structure. The public assignment title does not define demolition, piling, deck, fender, bollard, utility, dredging or pavement quantities.
Marine interfaces
Berth 19A is the North Quay berth in Dr Ambedkar Dock. The Ministry of Ports, Shipping and Waterways' 2024-25 Basic Port Statistics records a 198-metre quay with 8.5-metre draft for passenger, general-cargo and liquid-bulk use. Engineering and construction packaging therefore need to address a live dock, berth-pocket access, cargo pipelines or utilities, vessel mooring and interfaces with adjoining quay operations.
Commercial evidence boundary
The INR 5.074 million figure is the sanctioned value of IIT Madras project IC24251239CPCPTXNTPHOC, not a berth-construction budget or contract award. A construction bidder, subcontractor, accepted price and mobilisation date have not been published.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

IIT Madras listed the 19A audit and detailed-engineering assignment as ongoing

The official ledger identifies a named consultant and a 2024-27 engineering window, while leaving the construction design, procurement, contractor and mobilisation open.

Source

The owner-side engineering assignment started

Project IC24251239CPCPTXNTPHOC began its technical-audit and detailed-design period. This is an engineering milestone, not a notice to proceed for berth construction.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Technical-audit findings and retained, repaired or replaced structural elements
  • Issued-for-tender drawings, design basis and berth loading criteria
  • Construction tender, qualification route and package boundary
  • Awarded works contractor, accepted price and notice to proceed
  • Marine piling, deck, fenders, bollards, utilities and pavement scope
  • Dredging, berth-pocket depth and any sediment-management requirement
  • Phasing beside live Dr Ambedkar Dock operations and edible-oil traffic
  • As-built survey, load testing, navigation release and owner acceptance

Reporting status

Design, confirmed confidence

Last checked 1 August 2026 across 4 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 4