Project record
DPA's Cargo Berths 1-6 programme has widened beyond the fender-only work approved in 2022. The Board approved an INR 329.8 million block estimate and tender authority for upgraded fenders, while IIT Madras later recorded an INR 7.08 million fender-upgrade consultancy from November 2023 to May 2025. A July 2025 DPA EOI instead asks a consultant to test the earthquake-damaged berths, compare strengthening with new construction, prepare the DPR and EPC tender and supervise delivery. No consultant or EPC award is public.
India / Asia Pacific
Port infrastructure
DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified / Confirmed
1 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe new scope moved beyond fender replacement to NDT, repair-versus-new-build options, DPR and DBR, EPC tender preparation, bid support and construction supervision. The delivery solution and commercial parties remain open.
SourceThe ledger confirms S Nallayarasu, project IC23242045OEDEEN008228, a 2023-25 assignment window and INR 7.08 million sanctioned value, but it does not establish a fender works award or installation.
SourceResolution 47 approved INR 329.8 million for upgraded fenders across panels 1-50 and authorized later NIT, bid and L1 actions. The resolution itself does not prove that a tender or award followed.
SourceEvidence gap