Project record

Kandla Cargo Berths No. 1-6 upgrade

Kandla cargo berths with working bulk vessels and quay cranes at Deendayal Port

Deendayal Port Authority via Wikimedia Commons; GODL-India attribution supplied on the file page; crop shows the working Kandla cargo-berth line, not structural testing or construction at Berths 1-6

DPA's Cargo Berths 1-6 programme has widened beyond the fender-only work approved in 2022. The Board approved an INR 329.8 million block estimate and tender authority for upgraded fenders, while IIT Madras later recorded an INR 7.08 million fender-upgrade consultancy from November 2023 to May 2025. A July 2025 DPA EOI instead asks a consultant to test the earthquake-damaged berths, compare strengthening with new construction, prepare the DPR and EPC tender and supervise delivery. No consultant or EPC award is public.

Project signal

Design in India

Current status DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified Source confidence Confirmed

Location

India / Asia Pacific

Segment

Port infrastructure

Status

DPA is assessing berth-wide repair, strengthening or replacement for an intended EPC package; no expanded-consultant award, EPC tender or works contractor is verified / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Deendayal Port Authority
Delivery parties
Indian Institute of Technology Madras - fender-upgrade consultant for project IC23242045OEDEEN008228; principal investigator S Nallayarasu, Expanded structural-assessment, DPR and supervision consultant - no award verified by 1 August 2026, EPC contractor and specialist subcontractors - no tender or award verified by 1 August 2026
Contract route
DPA's 30 March 2022 Board resolution approved an INR 329.8 million fender block estimate and authorized the Chairman to issue an NIT, evaluate bids and accept an L1 bidder. It does not record those later actions as completed. DPA's July 2025 EOI states that the broader project is intended for EPC mode and requires the consultant to prepare tender documents, support bid evaluation and supervise construction. The EOI is not a consultant award or an EPC procurement.
Execution window
IIT Madras records the fender consultancy from 30 November 2023 to 30 May 2025. DPA's later berth-wide consultant EOI does not establish an awarded consultant, EPC notice to proceed or construction programme. Its supervision obligations extend through completion once a downstream contractor exists.
Works package
Assess Cargo Berths 1-6 through site survey, visual inspection, structural-health monitoring and NDT of decks, piles, beams and connections; compare repair and strengthening with new construction; establish phasing, schedule, cost, impacts and life extension; prepare the DPR, DBR, detailed analysis, design, drawings, estimates and implementation scheme; prepare EPC tender documents and support bid evaluation; then monitor and certify construction. The earlier fender-only scope remains a historical package boundary, not proof of installed equipment.
Marine interfaces
DPA says the six berths were built between 1955 and 1972 for roughly 45,000-55,000 DWT vessels with triple-cell 1000H fenders, were damaged in the 2001 earthquake and were temporarily repaired for operations. Cargo Berths 7-10 were later upgraded for 75,000 DWT vessels with 1450H fenders. The alignment offset between the berth groups now affects berthing, so structural condition, berth line, fender energy, mooring, live operations and staged vessel access must be resolved together.
Commercial evidence boundary
The INR 329.8 million figure is a 2022 block estimate for the fender proposal, not an accepted works price. The INR 7.08 million figure is the sanctioned value of the IIT Madras fender consultancy, not construction capex. No public primary record names the broader consultant, EPC contractor, fender manufacturer, installation subcontractor or awarded price.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

DPA reopened the programme as a berth-wide structural and EPC consultancy

The new scope moved beyond fender replacement to NDT, repair-versus-new-build options, DPR and DBR, EPC tender preparation, bid support and construction supervision. The delivery solution and commercial parties remain open.

Source

IIT Madras listed the fender-upgrade consultancy as ongoing

The ledger confirms S Nallayarasu, project IC23242045OEDEEN008228, a 2023-25 assignment window and INR 7.08 million sanctioned value, but it does not establish a fender works award or installation.

Source

The Board approved the fender block estimate and future tender authority

Resolution 47 approved INR 329.8 million for upgraded fenders across panels 1-50 and authorized later NIT, bid and L1 actions. The resolution itself does not prove that a tender or award followed.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Award and work order for the expanded structural-assessment and DPR consultant
  • NDT findings for decks, piles, beams and connections
  • Selection between repair and strengthening, partial reconstruction or new berths
  • Design basis for 75,000 DWT vessels and the alignment with Cargo Berths 7-10
  • Issued EPC tender, qualification criteria and package boundary
  • EPC award, accepted price, notice to proceed and construction phasing
  • Fender, bollard, pile, deck, cathodic-protection and concrete-repair suppliers
  • Live-port staging, temporary berth closures and cargo-continuity plan
  • Load testing, hydrographic checks, navigation release and final handover

Reporting status

Design, confirmed confidence

Last checked 1 August 2026 across 4 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 4