Port Engineering
Kandla 1-6 has moved beyond a fender-only scope
Kandla Cargo Berths 1-6 began with a 2022 Board-approved INR 329.8 million fender proposal and a later INR 7.08 million IIT Madras fender consultancy. DPA's July 2025 EOI widens the programme to structural testing, repair or new-build options, DPR and DBR, EPC tender preparation and construction supervision.
The owner reopened the structural solution
DPA's 2022 Board minutes approve an INR 329.8 million fender block estimate and future tender authority. IIT Madras records project IC23242045OEDEEN008228, S Nallayarasu, a 30 November 2023 to 30 May 2025 window and INR 70.80 lakh sanctioned value. DPA's July 2025 EOI documents the 1955-72 berths, 2001 earthquake damage, temporary repairs, existing 1000H fenders, alignment issue and broader EPC consultancy scope. The later consultant and works awards remain unpublished.
A scope reset changes the supplier map
The commercially relevant package is no longer limited to replacing berth furniture. Decks, piles, beams, connections, berth alignment, life extension, phasing and live-port operations now sit inside the option study. That could create a larger EPC package, but only after a consultant award, preferred concept and issued tender establish the design and quantities.
Evidence conclusion
Awards remain behind two procurement gates
The 2022 resolution authorized tender actions but did not record an award. IIT Madras is attributable only to the 2023-25 fender-upgrade consultancy. An expanded consultant work order, EPC RFP, EPC award, fender manufacturer and installation subcontractor all remain unpublished. The evidence supports design-stage monitoring, not contractor attribution.
Outstanding evidence
- Expanded-consultant award and work order
- NDT and structural-health findings
- Repair and strengthening versus new-berth decision
- Preferred berth line and 75,000 DWT design basis
- EPC tender documents and bidder qualification
- EPC award, accepted price and notice to proceed
- Fender, mooring, concrete-repair and piling specialist packages
- Berth closures, live-port phasing and final acceptance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- Minutes of DPA Board meeting dated 30 March 2022 Deendayal Port Authority, 30 March 2022
- Ongoing consultancy projects as of 31 March 2025 Indian Institute of Technology Madras, 31 March 2025
- EOI for appointment of consultant for upgradation of Cargo Berths 1-6 Deendayal Port Authority, 16 July 2025
- Tender page for appointment of consultant for existing Cargo Berths 1-6 Deendayal Port Authority, 16 July 2025