Project record

Kishorn Phase 1B East Quay development

Participation
Requires review
Submission deadline
Participation checked

Restricted selection and marine pre-application consultation for the proposed East Quay

Participation source

Kishorn's consultation materials describe a 150-metre piled quay, a possible temporary piling bund and mooring dolphins. The design introduces a larger vessel envelope while procurement and marine licensing proceed on separate schedules.

Kishorn schedule distinguishes 2 November selection submissions, 10 November consultation comments, 2 December intended invitations and conditional 2027 construction.

IMWO original engineering diagram; source: Kishorn Port / Public Contracts Scotland

Location

United Kingdom / Europe

Segment

Port infrastructure

Phase

Prequalification / Confirmed

Last checked

31 October 2026

Coverage

Related sectors

Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Kishorn Port Ltd
Procurement references
OCT565850; 844561
Delivery parties
Main works contractor to be selected; consultation materials prepared with Affric.
Contract route
Procurement references: 844561. Restricted procedure with SPD selection, applications due 2 November 2026 at 12:00 GMT and invitations expected 2 December. Notice indicates up to five selected firms. Access to detailed procurement documents is restricted; later clarification history needs confirmation.
Execution window
Consultation materials expect 2027 construction for up to 18 months. Marine-licence application and consent remain ahead of the proposed work.
Works package
New 150m piled East Quay with dolphins, infill and access works. The notice describes an existing 8.5ha reclamation from drydock enlargement; the consultation FAQ proposes 17,000m2 of East Quay reclamation.
Marine interfaces
Tubular and sheet piles, anchor piles and tie rods form the proposed quay structure. Possible temporary piling bund, rock movement, marine mammal controls and loch mooring movements affect the work sequence.
Commercial evidence boundary
GBP 30 million ex-VAT estimated procurement. Existing reclaimed ground, new permanent infill and a possible temporary piling bund require separate quantity, bearing-capacity and material-handling allowances.

Evidence gap

What remains unverified

Outstanding evidence

  • Tender drawings and quantities for existing ground, new infill and temporary bund material
  • Selection-stage notices, clarifications and 2 December invitation plan
  • Marine-licence application, piling controls and mooring arrangements

Reporting status

Project phase
Prequalification
Evidence confidence
Confirmed
Last checked
31 October 2026
Cited sources
4

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 4