Niedersachsen Ports is adding three heavy-load berths and about 38 hectares of terminal land between Cuxhaven's Europakai and berth 8. The owner defines a 1,250-metre project frontage. By November 2025, roughly 427 tubular piles and 250 raking piles had been installed; DEME reported in April 2026 that trailing suction hopper dredger Meuse River was carrying out rainbowing for the dredging and reclamation works.
Project signal
Construction in Germany
Record the project as an active marine construction programme, not a completed terminal. A continuous waterside pile line and current reclamation establish physical progress. Foundation piles, reinforced concrete, terminal equipment, roads, staged concession handover and operating readiness remain later parts of the programme.
Current statusSand reclamation is active behind the new quay line; phased terminal delivery runs through 2028Source confidenceConfirmed
Location
Germany / Europe
Segment
Port infrastructure
Status
Sand reclamation is active behind the new quay line; phased terminal delivery runs through 2028 / Confirmed
Evidence reviewed
20 July 2026
Controlled taxonomy
Related sectors
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Scope, counterparties, and execution logic
Client / authority
Niedersachsen Ports GmbH & Co. KG
Delivery parties
Arbeitsgemeinschaft Neubau der Liegeplatze 5 bis 7 - Tiefbau GmbH Unterweser, Heinrich Hirdes GmbH, Nordsee Nassbagger- und Tiefbau GmbH and DEPENBROCK Ingenieurwasserbau GmbH & Co. KG, DEME, Depenbrock, TAGU and Boskalis - consortium identified by DEME for the offshore-wind terminal expansion and current reclamation work, Cuxport GmbH - concessionaire for berths 5 and 6.1 and approximately 19 hectares of terminal area, Cuxhaven Terminal GmbH & Co. KG, a Blue Water Breb project company - concessionaire for berths 6.2 and 7 and a similar terminal area
Contract route
The approximately EUR 300 million port scheme combines public infrastructure funding with concession-backed private prefinancing. Niedersachsen Ports states that up to EUR 200 million comes from Germany's GRW regional-development programme and up to EUR 100 million is prefinanced by the port economy through concessions. The European Commission state-aid record for case SA.113780 gives a EUR 300 million overall budget and 67% aid intensity. Operating concessions divide the terminal between Cuxport and Cuxhaven Terminal/Blue Water Breb.
Execution window
The owner schedules sand filling from Q1 2026 to Q4 2027, foundation piles from Q3 2026 to Q4 2027, reinforced concrete during 2027, equipment from Q4 2027 to Q3 2028, and earth and road works from Q2 2026 to Q4 2028. Cuxport's berths 5 and 6.1 package is planned for 2027; the berths 6.2 and 7 package is planned for 2028, with overall completion by the end of 2028.
Works package
Three new berths, a heavy-load quay line, dredging and sand reclamation for about 38 hectares of terminal land, foundation piling, reinforced-concrete works, terminal equipment, earthworks and roads. The terminal is designed for handling and storing onshore and offshore wind components. The owner describes a 1,250-metre project frontage; DEME's contractor release describes 1,350 metres of heavy-load quay wall, so the two measurements should not be merged without a common measurement basis.
Marine interfaces
Construction works as a moving line along the waterfront. Five specialist piling units depend on tide windows to install and connect tubular and raking piles. Sand filling follows completed quay sections, and the owner says the hopper-dredger slot was booked in advance, making completion of preceding piling a direct schedule interface. Reclaimed ground then has to support foundation piles, concrete, heavy-load pavement, terminal equipment and concession handover.
Commercial read
The main marine civil works and both operating concessions are already allocated. Current work confirms demand for dredging, rainbowing and reclamation capacity rather than an unawarded owner package. Remaining opportunity is more likely to sit in disclosed subcontracts, materials, terminal fit-out, heavy-load surfaces, utilities, equipment integration, survey and handover support than in the core quay concession or main civil contract.
Next milestone
Evidence that reclamation has advanced across the planned terminal sections, followed by the scheduled foundation-pile and reinforced-concrete works and the first 2027 concession handover.
Material change register
What changed, when, and what it proves
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Meuse River began active reclamation work
DEME's project update shows the hopper dredger rainbowing inside the new quay line, moving at least part of the site from waterfront piling into terminal land formation.
The waterside pile line closed the 1,250-metre gap
Niedersachsen Ports reported approximately 427 tubular piles and 250 raking piles installed, with further raking-pile connection work continuing before sand filling.
Evidence that reclamation has advanced across the planned terminal sections, followed by the scheduled foundation-pile and reinforced-concrete works and the first 2027 concession handover.
Decision watchpoints
Completion status of remaining tubular and raking piles
Reclamation progress and settlement monitoring across the 38-hectare footprint
Foundation-pile and reinforced-concrete start by work section
Heavy-load pavement, drainage, utilities and road interfaces
Terminal equipment procurement and integration
Cuxport handover for berths 5 and 6.1 in 2027
Blue Water Breb handover for berths 6.2 and 7 in 2028
As-built surveys, load testing, permits and operational opening
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Evidence reviewed date is not a project-event date.
IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.
Evidence reviewed20 July 2026Sources in this record5
Source record
Niedersachsen Ports controls the project footprint, funding split, concessions, programme and November 2025 installed-pile record. DEME's 8 April 2026 release is the current evidence that Meuse River is actively rainbowing for dredging and land reclamation. It gives a 1,350-metre heavy-load quay-wall figure, while the owner repeatedly gives 1,250 metres for the project frontage. Both figures are retained with their source context rather than presented as interchangeable. The EU state-aid notice establishes the approved public-funding case, not construction completion.
Phase: construction. Evidence reviewed: 20 July 2026.