Queensland opened the Yorkeys Knob boating facility north of Cairns on 7 September 2023. Hall Contracting delivered a six-lane boat ramp, three floating walkways, two rock breakwaters, a dredged harbour basin and access channel, reclamation, queuing beaches and landside facilities. The official project total was AUD 22.4 million, while Queensland's TMR contract disclosure reports AUD 18,739,439 against Hall contract CN-15409.
Project signal
Completed in Australia
Current statusThe AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation worksSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Recreational harbour, breakwaters, dredging and boat-launch infrastructure
Status
The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works / Confirmed
Last checked
4 August 2026
Coverage
Related sectors
Recreational harbour, breakwaters, dredging and boat-launch infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Queensland Department of Transport and Main Roads / Maritime Safety Queensland and Cairns Regional Council
Delivery parties
Hall Contracting Pty Ltd - principal construction contractor under CN-15409, Marine, rock-supply, walkway and landside subcontractors - not named in the cited owner records
Contract route
Queensland TMR's open-procurement contract disclosure identifies CN-15409, Hall Contracting Pty Ltd and AUD 18,739,439. The State and Cairns Regional Council jointly funded the AUD 22.4 million facility, with Council contributing AUD 3.5 million. None of the cited sources provides the final account, variation schedule or subcontractor register.
Execution window
On-site work began in February 2022 and the facility opened in early September 2023. Hall reported completing dredging and reclamation during the build before moving to the ramp and breakwater workfronts. The completion release records more than 55,000 work-hours and over 40 supported jobs.
Works package
The completed marine scope comprises a six-lane concrete boat ramp, three floating walkways, two rock-armour breakwaters, a dredged basin and access channel, reclamation and queuing beaches. Hall reported dredging about 20,000 m3 from Half Moon Bay and reusing the material to form the platform. Landside works added an access road, footpath, amenities, protective fencing, 135 car-trailer bays and 63 car spaces.
Marine interfaces
The two breakwaters shelter the launch basin from wave action and prevailing weather, while the dredged basin and access channel provide the navigable route between the ramp and Half Moon Bay. Delivery linked dredging, beneficial reuse, reclamation settlement, rock-armour placement, ramp levels, floating-walkway connections and water-quality monitoring inside the Great Barrier Reef Marine Park.
Commercial evidence boundary
This completed scheme provides an integrated small-harbour delivery benchmark rather than a current construction lead. Comparable opportunities sit across design, dredging and reuse, armour-rock logistics, breakwaters, ramps, floating access, water-quality controls and lifecycle maintenance. The ownership split matters: Maritime Safety Queensland owns the in-water assets, while Cairns Regional Council manages the facility.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The State confirmed the six-lane ramp, three floating walkways, two breakwaters, dredged basin and access channel were complete and available to users.
A dated TMR compliance record identified Hall Contracting and the Yorkeys Knob Boat Ramp Project during early site activity, independently anchoring the contractor's mobilisation.