Project record

Yorkeys Knob boating facility

Aerial construction view of Yorkeys Knob boating facility showing the new rock breakwaters, reclaimed platform and marine workfront

Hall Contracting; exact-project construction image

Queensland opened the Yorkeys Knob boating facility north of Cairns on 7 September 2023. Hall Contracting delivered a six-lane boat ramp, three floating walkways, two rock breakwaters, a dredged harbour basin and access channel, reclamation, queuing beaches and landside facilities. The official project total was AUD 22.4 million, while Queensland's TMR contract disclosure reports AUD 18,739,439 against Hall contract CN-15409.

Project signal

Completed in Australia

Current status The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works Source confidence Confirmed

Location

Australia / Asia Pacific

Segment

Recreational harbour, breakwaters, dredging and boat-launch infrastructure

Status

The AUD 22.4 million facility opened in September 2023 after Hall Contracting delivered the ramp, floating walkways, two breakwaters, dredged basin, access channel and reclamation works / Confirmed

Last checked

4 August 2026

Coverage

Related sectors

Recreational harbour, breakwaters, dredging and boat-launch infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Queensland Department of Transport and Main Roads / Maritime Safety Queensland and Cairns Regional Council
Delivery parties
Hall Contracting Pty Ltd - principal construction contractor under CN-15409, Marine, rock-supply, walkway and landside subcontractors - not named in the cited owner records
Contract route
Queensland TMR's open-procurement contract disclosure identifies CN-15409, Hall Contracting Pty Ltd and AUD 18,739,439. The State and Cairns Regional Council jointly funded the AUD 22.4 million facility, with Council contributing AUD 3.5 million. None of the cited sources provides the final account, variation schedule or subcontractor register.
Execution window
On-site work began in February 2022 and the facility opened in early September 2023. Hall reported completing dredging and reclamation during the build before moving to the ramp and breakwater workfronts. The completion release records more than 55,000 work-hours and over 40 supported jobs.
Works package
The completed marine scope comprises a six-lane concrete boat ramp, three floating walkways, two rock-armour breakwaters, a dredged basin and access channel, reclamation and queuing beaches. Hall reported dredging about 20,000 m3 from Half Moon Bay and reusing the material to form the platform. Landside works added an access road, footpath, amenities, protective fencing, 135 car-trailer bays and 63 car spaces.
Marine interfaces
The two breakwaters shelter the launch basin from wave action and prevailing weather, while the dredged basin and access channel provide the navigable route between the ramp and Half Moon Bay. Delivery linked dredging, beneficial reuse, reclamation settlement, rock-armour placement, ramp levels, floating-walkway connections and water-quality monitoring inside the Great Barrier Reef Marine Park.
Commercial evidence boundary
This completed scheme provides an integrated small-harbour delivery benchmark rather than a current construction lead. Comparable opportunities sit across design, dredging and reuse, armour-rock logistics, breakwaters, ramps, floating access, water-quality controls and lifecycle maintenance. The ownership split matters: Maritime Safety Queensland owns the in-water assets, while Cairns Regional Council manages the facility.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Queensland opened the completed boating facility

The State confirmed the six-lane ramp, three floating walkways, two breakwaters, dredged basin and access channel were complete and available to users.

Source

TMR site records confirmed Hall on the workfront

A dated TMR compliance record identified Hall Contracting and the Yorkeys Knob Boat Ramp Project during early site activity, independently anchoring the contractor's mobilisation.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Maintenance-dredging trigger and surveyed access-channel depths
  • Breakwater settlement, armour displacement and storm performance
  • Floating-walkway condition and accessibility
  • Ramp surface, toe protection and launch-lane availability
  • Final contract value and disclosed variations
  • Water-quality and Great Barrier Reef Marine Park compliance
  • MSQ and Council maintenance responsibilities and budgets
  • Named subcontractors and material suppliers for benchmarking

Reporting status

Completed, confirmed confidence

Last checked 4 August 2026 across 5 cited sources. The dated timeline above carries the project events.