Completed Project Boundaries

Yorkeys Knob packages a small harbour into one completed build

Published 4 August 2026 Publisher IMWO Region Asia Pacific Confidence Confirmed
Aerial construction view of Yorkeys Knob boating facility showing rock breakwaters, the reclaimed platform and marine construction plant

Hall Contracting; exact Yorkeys Knob construction image

Yorkeys Knob opened in September 2023 with a six-lane ramp, three floating walkways, two rock breakwaters, dredged basin, access channel and reclaimed landside platform. Hall Contracting delivered the integrated workfront and reports approximately 20,000 m3 of dredging. Queensland gives AUD 22.4 million as the total project cost; its TMR contract disclosure lists AUD 18,739,439 for Hall contract CN-15409. Those figures describe the programme and prime contract respectively.

The opening closes construction and opens a maintenance ledger

Queensland's completion release controls opening, facility scope, total project value and ownership split. TMR's disclosure controls CN-15409, Hall Contracting and the AUD 18.739 million contract value. Hall's pages supply the approximately 20,000 m3 dredging and beneficial-reuse sequence. They do not identify the full lower-tier chain or final account. The visual shows the exact construction workfront before opening.

One workfront joined marine access and landside capacity

Completed small harbours are commercially valuable when the delivery boundary remains visible. Yorkeys Knob links dredging to reuse, reuse to reclamation, reclamation to parking and ramp levels, and breakwaters to basin operability. Its ownership model also changes who buys future work: Maritime Safety Queensland owns the in-water infrastructure, while Cairns Regional Council manages the public facility.

Evidence conclusion

The interface chain defines the delivery benchmark

Hall dredged Half Moon Bay material to form the basin and access channel, then reused it in the platform supporting 135 car-trailer bays and 63 car spaces. Two armour breakwaters protect the launch area, and floating walkways connect users to six ramp lanes. Future signals should be maintenance-specific: bathymetric surveys, channel infill, armour displacement, walkway defects, ramp condition and owner-funded renewal, not continuation of the original build.

Outstanding evidence

  • Post-opening bathymetry and maintenance-dredging trigger
  • Breakwater armour and settlement inspections
  • Floating-walkway, ramp and accessibility maintenance
  • Hall contract variations and final account
  • MSQ and Council renewal procurement