Toddy Civil Engineering received the USD 1.174m works contract on 11 June 2024 and KEMFSED recorded the October 2024 groundbreaking; no later completion or acceptance evidence has been published
The State Department for the Blue Economy and Fisheries awarded Toddy Civil Engineering Co. Limited the Kipini Fish Landing Site works contract for USD 1,173,854.51. The package combines fish-handling buildings and sanitation with a boat-repair yard, gear-mending shed, slip, access, drainage, wastewater treatment and electrical works on a 4.6-acre coastal site in Tana River County. KEMFSED recorded a formal groundbreaking in October 2024.
KEMFSED Kipini ESIA, page 90; official site-boundary aerial, not evidence of completed works
Kenya / Africa
Port infrastructure
Construction / Confirmed
3 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe official project newsletter confirms a physical launch in October 2024, moving the record beyond award without establishing production quantities or completion.
SourceWorld Bank contract 1792980 identifies Toddy Civil Engineering, reference KE-MOMBE&MA-TR-2024-012-CW and USD 1,173,854.51 committed supplier value, while excluding downstream subcontract awards.
SourceEvidence gap