DP World is expanding London Gateway with two additional all-electric berths. McLaughlin & Harvey is the confirmed contractor for the fifth-berth quay works, where Port of London Authority notices trace a 430-metre extension, steel tubular piling and named marine plant. Gobion separately reports a GBP 52 million contract for ten automated-stacking-crane yard modules. The quay-wall milestone does not establish completion of the yard, cranes, automation or commercial opening.
Project signal
Construction in United Kingdom
Current statusPort of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027Source confidenceConfirmed
Location
United Kingdom / Europe
Segment
Deep-water ports and automated container terminals
Status
Port of London Authority reported the 430-metre Berth 5 quay extension complete by 1 August 2026 while further retaining-wall piling continued toward the Berth 6 interface; the separately contracted ten-module automated yard remains on a contractor-reported programme to March 2027 / Confirmed
Last checked
1 August 2026
Coverage
Related sectors
Deep-water ports and automated container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
DP World London Gateway, owner and operator of the Thames deep-water container terminal
Delivery parties
McLaughlin & Harvey - confirmed contractor for the Berth 5 quay works and steel tubular pile installation, Gobion - contractor-reported award for the separate ten-module automated container yard, including pavements, ASC rails and foundations, reefer plinths, drainage, utilities, substations, 11kV distribution and SCADA, Neptune 585 Eurobarge, Neptune NP674 barge, mult-cat Felix or similar, WSB Resolute and associated support craft - plant named in Port of London Authority notices; the notices do not convert every plant owner or operator into a confirmed subcontractor, No reviewed primary record allocates the Berth 5 quay cranes, automation systems, equipment commissioning or all downstream electrical and marine subcontracts to named suppliers
Contract route
DP World is funding a wider GBP 1 billion two-berth expansion. McLaughlin & Harvey is delivering the marine quay works for Berth 5. An official Find a Tender notice separately described the automated yard as a ten-module civil and electrical package with an estimated GBP 60 million value; Gobion later reported securing that package for GBP 52 million.
Execution window
DP World announced construction from May 2025 within a four-year two-berth programme. Marine piling was expected from August 2025 for about 18 months. The PLA stated on 1 August 2026 that the 430-metre Berth 5 extension was complete while a further 75 metres of retaining-wall piling continued into the Berth 6 formation. Gobion reports its yard programme running from late March 2026 to March 2027.
Works package
Extend the quay for Berth 5 and deliver a separate automated container yard with ten ASC modules, heavy-duty pavement, ASC rails and foundations, reefer and container plinths, drainage, utilities, substations, 11kV distribution, SCADA and live-terminal tie-ins. The wider DP World programme adds two 400-metre all-electric berths and a second rail terminal.
Marine interfaces
The tubular-pile quay and retaining wall must be released into a separate yard, crane, power, automation and operating-terminal integration sequence. PLA notices establish the marine geometry and plant window; they do not evidence yard acceptance, crane commissioning, terminal operating-system readiness or commercial service.
Commercial evidence boundary
The top-tier marine and yard packages are visible, but the interface ledger below them remains incomplete. The strongest current milestone is physical completion of the 430-metre Berth 5 extension. The yard award value is supplier-reported, while integrated handover and a Berth 5 opening date remain unconfirmed.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The contractor separated ten yard modules and associated civil, power and controls work from the quay package, with a reported March 2027 completion target.