Package Boundary
London Gateway Berth 5 quay is not the whole terminal
DP World; London Gateway terminal operations image accompanying the expansion programme
Port of London Authority reported the 430-metre Berth 5 extension complete by 1 August 2026. That milestone closes a physical quay scope, not the whole terminal. McLaughlin & Harvey holds the quay package, while Gobion separately reports a GBP 52 million ten-module automated-yard contract running to March 2027.
The quay milestone exposes a separate yard and systems chain
PLA controls the physical marine milestone. McLaughlin & Harvey controls its quay role. Find a Tender defines the yard scope and estimate; Gobion reports the award value and programme. DP World controls the wider two-berth expansion, not each downstream package status.
Physical quay completion precedes terminal readiness
The package split prevents premature operating-status claims and makes the remaining supply chain visible: ASC rails and foundations, substations, 11kV distribution, SCADA, cranes, automation, live-terminal tie-ins and integrated acceptance.
Evidence conclusion
Keep marine, yard and operating releases separate
PLA notices provide unusually strong marine evidence, including the 430-metre geometry, work plant and a further 75 metres of retaining-wall piling toward Berth 6. The yard's GBP 52 million value is contractor-reported against the official tender's GBP 60 million estimate. Integrated Berth 5 handover and commercial opening remain unverified in the cited sources.
Outstanding evidence
- Gobion's March 2027 yard programme
- ASC rail and foundation acceptance
- Substation, 11kV and SCADA commissioning
- Quay-crane and automation supplier allocation
- Further retaining-wall works toward Berth 6
- Integrated operating release
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Berth 5 completion and Berth 6 interface notice L6-26 Port of London Authority, Updated 1 August 2026
- London Gateway Berth 5 construction works McLaughlin & Harvey, Current project notice reviewed 1 August 2026
- Berth 5 container yard tender UK Find a Tender, Published 2025
- DP World Gateway automated yard Gobion, Current project page reviewed 1 August 2026
- London Gateway construction start DP World, 21 March 2025