FIDELE SARL's rehabilitation contract was signed 5 February 2025 for an operating export-approved landing facility; no controlled site start, temporary operating setup or physical progress evidence through 8 August 2026
FIDELE SARL signed the Ouakam fishing-quay rehabilitation contract under P175915 on 5 February 2025, with a USD 692,616.10 supplier commitment. SENRM's land diagnostic describes an operating, export-approved 1,050 m2 landing facility requiring restructuring and extension, alongside a nonfunctioning 250 m2 ice plant, 530 m2 storage shed and 1,510 m2 fisher house on a 4,000 m2 parcel. The preparation documents propose a temporary lightweight facility to maintain fish-trading continuity. Site handover, temporary-facility readiness, mobilisation and completion remain unconfirmed through 8 August 2026.
Fish landing quay and fisheries value-chain infrastructure
Phase
Award / Confirmed
Last checked
8 August 2026
Coverage
Related sectors
Fish landing quay and fisheries value-chain infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Senegal Ministry of Fisheries and Maritime and Port Infrastructure through the SENRM project implementation structure, World Bank project P175915
Delivery parties
FIDELE SARL - supplier name in the World Bank award dataset; exact legal identity, consortium structure and lower tiers not disclosed, Temporary operating-facility contractor, designer, supervision consultant, marine subcontractors, ice-plant and fish-handling suppliers - not identified
Contract route
The rehabilitation package used a post-review request for bids under AON-T-SENRM-MPEM/01. Contract record 1854465 identifies FIDELE SARL and the 5 February 2025 signing. The current plan retains the main works as signed; no separate temporary-facility award has been identified.
Execution window
FIDELE SARL signed on 5 February 2025. The October 2024 land diagnostic defines the live-site continuity approach but supplies no notice-to-proceed or works baseline. Site possession, temporary-setup completion, mobilisation, progress, taking-over and commissioning dates remain unconfirmed.
Works package
Restructure and extend the existing fishing landing facility and improve fish-handling equipment and services while maintaining operations. The preparation record identifies the 1,050 m2 landing facility, a 250 m2 nonfunctioning ice plant, 530 m2 storage shed and 1,510 m2 fisher house, and proposes a temporary lightweight structure and controlled mini-market arrangement during rehabilitation. Final permanent-work quantities and equipment schedules remain unpublished.
Marine interfaces
The works must keep pirogue access, fish landing, traders and mini-market activity functioning on a constrained Atlantic frontage exposed to sea advance. Temporary routing, user separation, marine access, ice and cold-chain continuity, sanitation, drainage and safe handover are therefore acceptance-critical interfaces rather than secondary social measures.
Commercial evidence boundary
The main rehabilitation contract carries a USD 692,616.10 supplier commitment, below the current-plan estimate of USD 821,184. The difference is a procurement baseline comparison, not a verified saving or final cost. Temporary-facility cost, variations, measured quantities, payments and final account remain undisclosed.
Contract and delivery chain
Work packages and named roles
Published scope, named parties and supporting evidence for each workstream.