Fishing Ports

Ouakam's live landing site makes temporary operations a delivery gate

Published 8 August 2026 Publisher IMWO Region Africa Confidence Confirmed
Official schematic map of the Ouakam fishing quay operating site, temporary operations interface, rehabilitation area and ocean frontage

SENRM; exact Ouakam March 2024 land-use map published in the October 2024 diagnostic, preparatory evidence only and not a works-progress image

FIDELE SARL's USD 692,616.10 rehabilitation contract was signed on 5 February 2025. SENRM's diagnostic identifies an operating, export-approved 1,050 m2 landing facility, a nonfunctioning ice plant and related storage and user assets. It proposes a temporary lightweight facility and mini-market arrangements so fish handling can continue during works. No controlled source confirms that temporary setup, site handover or mobilisation.

Operating continuity sits before permanent rehabilitation

World Bank award data controls FIDELE SARL, the contract amount and signing date. SENRM's diagnostic controls existing-asset dimensions, operating status and the temporary-continuity concept. The map and planning recommendations are not used as evidence that mobilisation has occurred. No controlled post-award site milestone has been located.

Acceptance must cover service continuity as well as concrete

Ouakam is not a vacant greenfield site. Pirogue landing, fresh-fish handling, traders, the mini-market and export-related operations share a constrained Atlantic frontage. A works start without a functioning temporary arrangement would transfer construction risk directly into food handling, marine access and local livelihoods.

Evidence conclusion

A live-site handover sequence remains undisclosed

The diagnostic maps a 4,000 m2 operating parcel and identifies no current land conflict in the targeted landing area, but it also records ageing assets, sea advance and a failed ice plant. The contract baseline should therefore be tested against temporary routing, marine access, hygiene, ice and cold-chain continuity, user segregation and final operating release. The difference between the USD 821,184 plan estimate and USD 692,616.10 award commitment is not a verified saving until scope and final account are reconciled.

Outstanding evidence

  • Approved temporary facility and mini-market plan
  • Site possession and notice to proceed
  • Pirogue access and fish-landing continuity
  • Structural rehabilitation and extension milestones
  • Ice plant, storage and fish-handling equipment suppliers
  • Hygiene, drainage and sanitation acceptance
  • Export-approval continuity and operating handover
  • Variations, final account and defects close-out