Busan Port Authority is delivering two 4,000-TEU-plus berths across a 700-metre quay and 546,000-square-metre site at West Container Terminal Phase 2-6. The 23-caisson substructure was completed in August 2024. Civil works remain associated with HL D&I Halla, while separate July 2024 awards cover six container cranes from HD Hyundai Samho and 34 transfer cranes from HJ Shipbuilding & Construction.
Project signal
Construction in South Korea
Current statusBPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening targetSource confidenceConfirmed
Location
South Korea / Asia Pacific
Segment
Deep-water ports and automated container terminals
Status
BPA completed the 23-caisson substructure in August 2024 and is advancing superstructure and automated-equipment packages toward an October 2027 completion and second-half 2027 opening target / Confirmed
Last checked
1 August 2026
Coverage
Related sectors
Deep-water ports and automated container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Busan Port Authority (BPA), port developer, facility owner and project client
Delivery parties
HL D&I Halla - identified civil contractor for the West Container Terminal Phase 2-6 construction works, HD Hyundai Samho - July 2024 contractor for six container cranes under a KRW 163.2 billion package, HJ Shipbuilding & Construction - July 2024 contractor for 34 transfer cranes, with installation targeted by June 2027, KR Engineering - present in BPA's transfer-crane production event; exact current supervision scope not allocated without further primary evidence, Public primary sources do not name the Phase 2-6 terminal operator, civil subcontractors, commissioning integrator or downstream marine plant providers
Contract route
BPA is delivering the civil terminal and procuring domestic automated cargo-handling equipment in separate packages. HL D&I Halla is identified on the civil works. BPA signed July 2024 contracts with HD Hyundai Samho for six container cranes and HJ Shipbuilding & Construction for 34 transfer cranes.
Execution window
BPA states a 2013-2027 project period, substructure completion in August 2024 and superstructure completion plus operating preparation by October 2027. Six quay cranes were scheduled for 18 barge shipments from October 2025 through June 2026. Transfer-crane installation is targeted for June 2027, ahead of a second-half 2027 opening target.
Works package
Deliver two berths for vessels above 4,000 TEU, a 700-metre quay, 546,000 square metres of terminal land, 23 caissons, civil superstructure and automated cargo-handling equipment including six container cranes and 34 transfer cranes.
Marine interfaces
Completed caisson and substructure works establish the quay platform, but berth structures, landside superstructure, crane block transport, final assembly, utilities, automation, commissioning and nautical readiness remain separate. Each quay crane travels in three blocks, creating 18 barge movements rather than 18 cranes.
Commercial evidence boundary
BPA provides unusually clear package values and production milestones. The public record still does not name a Phase 2-6 operator or civil subcontract chain, allocate the KRW 624.819 billion total across all current awards, or publish integrated testing, berth acceptance and operating-release evidence.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
HJ Shipbuilding & Construction began the separate 34-unit yard-equipment package, with production and installation continuing toward the June 2027 target.
BPA records all 23 caissons installed and the substructure complete, while superstructure, equipment integration, commissioning and operating readiness remained open.