Project record

Noatum Ports Pointe-Noire Terminal

AD Ports Group, Republic of the Congo and contractor representatives at the Noatum Ports Pointe-Noire contract-award ceremony

AD Ports Group; exact 18 May 2026 Noatum Ports Pointe-Noire contract-award event

Noatum Ports Pointe-Noire is a new multipurpose terminal under a separate concession from Congo Terminal's expansion. AD Ports Group holds 51% of the operating venture and CMA Terminals 49%. In May 2026 AD Ports awarded a USD 150 million marine and topside package to the MAR Contracting-MBTP joint venture and a USD 50 million equipment package to ZPMC for three STS and nine hybrid RTG cranes.

Project signal

Award in Republic of the Congo

Current status AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years Source confidence Confirmed

Location

Republic of the Congo / Africa

Segment

Deep-water ports and container terminals

Status

AD Ports Group awarded two marine and topside contracts to the MAR Contracting-MBTP joint venture and a crane contract to ZPMC on 18 May 2026; the 420-metre terminal is expected to be built over approximately two years / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Noatum Ports Pointe-Noire, the AD Ports Group (51%) and CMA Terminals (49%) joint venture operating under a 30-year extendable concession with the Republic of the Congo
Delivery parties
MAR Contracting SARLU-MBTP SA joint venture - design and construction of the quay wall, marine structures, crane foundations, quay infrastructure and associated waterside works, MAR Contracting SARLU-MBTP SA joint venture - topside yard, buildings, utilities, substations and supporting infrastructure, ZPMC - three ship-to-shore cranes and nine hybrid rubber-tyred gantry cranes, AD Ports Group - majority venture partner, terminal developer and award authority, CMA Terminals - 49% venture partner and future operating partner, No reviewed primary source identifies a dredging contractor, downstream marine subcontractors or the complete systems and buildings supply chain
Contract route
AD Ports Group signed a 30-year concession in June 2023, extendable by 20 years, and formed a majority-owned operating venture with CMA Terminals in February 2025. Its 2025 annual report recorded ESIA approval and an advancing EPC tender. In May 2026 it awarded two civil contracts to the MAR-MBTP joint venture and a separate crane contract to ZPMC.
Execution window
The concession was signed in June 2023 and the AD Ports-CMA venture announced in February 2025. Three main contracts were awarded on 18 May 2026. AD Ports expects construction to complete in approximately two years, placing the current target around 2028 subject to mobilisation and acceptance.
Works package
Develop a multi-user multipurpose terminal with a 420-metre quay, approximately 16 metres of water depth, a 100,000-square-metre logistics area, three STS cranes and nine hybrid RTGs. The marine package includes the quay wall, marine structures, crane foundations, quay infrastructure and associated waterside works; the topside contract covers the yard, buildings, utilities and substations.
Marine interfaces
Quay-wall design, marine structures, crane foundations, waterside works, yard levels, substations and ZPMC equipment must be aligned before integrated testing. The award identifies a 16-metre terminal depth but not the dredging contractor or acceptance survey, so navigational access remains an unallocated interface rather than a confirmed dredging package.
Commercial evidence boundary
The top-tier concession, equity and three-contract chain is public, including a combined USD 200 million award value. Mobilisation, notices to proceed, downstream subcontractors, ground conditions, dredging responsibility, detailed commissioning gates and final completion remain open. The broader concession investment estimate exceeds the value of these three awards.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Three terminal contracts were awarded

AD Ports committed USD 150 million to the MAR-MBTP marine and topside joint venture and USD 50 million to ZPMC's crane package, moving the project from tender into award.

Source

AD Ports and CMA Terminals formed the operating venture

The 51/49 venture assigned majority control to AD Ports and a 49% operating stake to CMA Terminals before package tendering.

Source

The terminal concession was signed

A 30-year concession, extendable by 20 years, gave AD Ports the development and operating mandate that preceded environmental review and package tendering.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • MAR-MBTP notice to proceed and mobilisation
  • Quay-wall design basis, foundation type and ground treatment
  • Whether dredging is owner-supplied or separately contracted
  • ZPMC crane fabrication, shipping and commissioning schedule
  • Substation, yard-system and building package allocation
  • Completion target and concession operating-release gates
  • Downstream subcontract and local-content disclosures

Reporting status

Award, confirmed confidence

Last checked 1 August 2026 across 6 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 6