Project record
Rotterdam's Yangtzekanaal programme has moved from a three-phase access plan through a completed 500-metre tug quay and into the 1,450-metre inland-shipping quay. A vibration-driven method change, enabling cofferdam, sand reuse and live-channel work notices expose the delivery mechanics; post-2028 channel dredging remains a separate package.
Netherlands / Europe
Port infrastructure
Phase A tug quay complete; Phase B inland-shipping quay started; Phase C dredging remains a post-2028 package / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The current owner page advances the programme from Phase A wall installation and Phase B design into a completed 12-berth tug quay and active 1,450-metre inland-shipping quay. Phase B berth, shore-power, heavy-load and operating acceptance remain open, with Phase C dredging scheduled after 2028.
Read controlling sourceThe 2025 annual report identifies a 1,500 by 40 metre temporary watertight structure for Phase B and early material reuse, while recording that the next investment decision and permit still followed at that reporting point. The current programme page later supersedes that planning state with Phase B award and start.
Read controlling sourceThe notice placed work vessels, stone removal, sheet-pile removal and installation, and dredging in the live channel from 24 November 2025 to 6 March 2026. It is field-execution and navigation-control evidence, not proof of completed quay or accepted channel geometry.
Read controlling sourceUnexpected vibration and settlement risk beside the Rhenus warehouse stopped conventional piling. The team adopted a 30-metre trench with cement-bentonite so foundation pipes and sheet piles could sink into place; the wall was installed by publication, while final section completion remained a later gate.
Read controlling sourceThe first stage of the two-phase contract moved the inland-shipping quay into contractor-supported design optimisation through the end of 2025. It did not by itself establish the implementation award, price, construction start or accepted berth system.
Read controlling sourceThe authority's 2023 year-end record confirms field execution began on the 500-metre quay and 12 tug berths. Shore power, berth operation and the later Phase B and C outcomes remained unresolved.
Read controlling sourceThe owner award fixed the 500-metre quay, 12-berth scope and contractor consortium, and anticipated work after summer. Contract signature did not prove mobilisation, installed wall, commissioning or the award of later phases.
Read controlling sourceThe programme separated tug berths, inland-shipping berths and later navigation-channel dredging, with different vessel-access objectives. At that point there were no contracts, construction records or achieved-access evidence.
Read controlling sourceDelivery watch
Track dated Phase B quay-wall execution, confirmation of the implementation award boundary and price if published, progress on the 30 berths, shore-power and heavy-load systems, 2028 civil and operating handover, and a separate Phase C procurement record defining dredging method, quantities, sediment route, channel geometry, navigational aids, and acceptance hydrography.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe March 2023 owner page and one-pager define three packages and separate 18,000, 24,000 and future 30,000 TEU navigation objectives. Contracts for the 500-metre Phase A tug quay were signed with Hakkers, Van Oord and De Klerk on 19 June 2023, and the authority's year-end record says field work began that September. The current programme page records a September 2024 Phase B construction-team award and a later implementation stage, but does not disclose a separate implementation award date or price. The authority's May 2025 technical feature records a temporary stop after 30-metre piles caused unacceptable vibration and settlement risk, followed by a 30-metre trench, cement-bentonite and vibration-free foundation-pipe and sheet-pile method; by publication the wall was installed, while completion remained scheduled for spring 2026. The 2025 annual report separately says Phase A included a 1,500 by 40 metre temporary watertight cofferdam for Phase B and reused 80,000 cubic metres of sand while the next investment decision and permit were still pending at that reporting point. A November 2025 harbourmaster notice confirms south-bank sheet-pile and dredging activity with work vessels in the live channel. The current programme page now marks Phase A complete and Phase B started, superseding the earlier planning state, while Phase C remains after 2028 without a published dredging award or accepted channel geometry.
Phase: construction. Evidence reviewed: 15 July 2026.