The Port of Edmonds Commission unanimously authorized staff on 8 June 2026 to enter Contract 2026-577 with TRICO Companies LLC. Despite the formal title North Portwalk and Seawall Reconstruction Phase II, the award is a site-preparation and marina-electrification package. It covers old-building demolition, M and N dock and Guest Moorage electrical upgrades, a future-restroom water stub, parking access and paving. The owner assigns actual seawall reconstruction and Portwalk structural upgrades to a separate Phase III programme.
Project signal
Award in United States
Current statusThe Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026Source confidenceConfirmed
Location
United States / Americas
Segment
Marina electrical infrastructure, waterfront site preparation and public realm
Status
The Port of Edmonds Commission unanimously authorized a contract with TRICO Companies LLC on 8 June 2026; the current owner page marks Phase II in progress and estimates work will begin late in 2026 / Confirmed
Last checked
12 August 2026
Coverage
Related sectors
Marina electrical infrastructure, waterfront site preparation and public realm is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Port of Edmonds
Delivery parties
TRICO Companies LLC - construction prime under Contract 2026-577, Wood Harbinger - electrical designer retained for construction-phase technical support, Selected electrical subcontractor - selection acknowledged in Commission minutes, identity not disclosed, Demolition, paving, striping, water, traffic-control and other lower tiers - not named in the cited public records
Contract route
The Port advertised Project 2026-577 as a competitive sealed-bid, traditional bid-build contract with a USD 2.9 million engineer estimate, a 15% apprenticeship requirement and bid, payment and performance security. Bids closed on 8 June 2026. The Commission authorized staff that evening to contract with TRICO after noting a narrow bid spread, relevant project experience and a selected electrical subcontractor with City of Edmonds public-works experience. The authorization is formal award approval; the cited minutes do not publish the executed signature date.
Execution window
The bid notice requires substantial completion by 1 May 2027. The current Port page estimates work will begin at the end of 2026. Washington L&I's contractor intent filing lists 5 October 2026 as Expected Work Start Date; that filing is not notice to proceed, confirmed mobilisation or physical-start evidence.
Works package
Phase II covers the south parking lot and former 336 Admiral Way administration parcel; demolition of the old administration building; electrical upgrades serving M Dock, N Dock and Guest Moorage; installation of Port-furnished electrical components; a water-service stub for the future Phase III restroom; new parking access, asphalt overlay, striping and associated site preparation. The owner describes the phase as enabling a future public plaza and Phase III, not constructing the later plaza or seawall works in full.
Marine interfaces
The work sits inside an operating marina beside active moorage, the north Portwalk and a constrained waterfront parking footprint. The delivery challenge is continuity of marina access and electrical service while replacing landside distribution infrastructure and preparing later waterfront works. The Commission specifically tested TRICO's experience with specialised marine electrical work and constrained sites; Wood Harbinger remains involved to support the electrical design during construction.
Commercial evidence boundary
Three official amount bases describe different layers. Washington L&I records USD 2,521,449.52 as Contract Total for project ID 1253328. The bid notice gives a USD 2.9 million engineer estimate. The current Port project page estimates the complete Phase II at USD 3.2 million and identifies USD 1.5 million from a WSDOT port-electrification grant plus USD 500,000 from an RCO ALEA grant, with the remainder from Port reserves. These are contract, pre-bid and programme-level figures respectively and are not additive.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Construction prime
Contract 2026-577
Named party
TRICO Companies LLC
Status
Confirmed
Source position
The Port Commission unanimously authorized staff on 8 June 2026 to enter the Phase II construction contract with TRICO. Source
Registered contract value
Washington L&I project ID 1253328
Named party
Port of Edmonds and TRICO Companies LLC
Status
Confirmed
Source position
The L&I Public Works Project Details row records USD 2,521,449.52 as Contract Total and identifies traditional bid-build delivery. Source
Electrical design support
M/N docks and Guest Moorage electrical upgrades
Named party
Wood Harbinger
Status
Confirmed
Source position
Commission minutes state that the electrical design team will remain involved during construction for technical support. Source
Electrical installation subcontract
Marina electrical installation
Named party
Selected but publicly unnamed electrical subcontractor
Status
Reported
Source position
Commission minutes confirm selection and City of Edmonds public-works experience but do not disclose the company name, value or exact allocation.
Actual seawall and Portwalk reconstruction
Phase III
Named party
Future procurement not allocated to Contract 2026-577
Status
Confirmed
Source position
The owner assigns seawall repair, steel-pile reinforcement, framing, decking, railings, lighting and public-realm upgrades to Phase III, estimated at USD 29.4 million. Source
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The current project page says engineering, design, funding and permitting are complete, estimates a late-2026 start and separates the USD 29.4 million Phase III seawall works.
Commission authorized the TRICO construction contract
The unanimous authorization fixes the selected prime and records Wood Harbinger's continued electrical design support while leaving the electrical subcontractor unnamed.
The project filing identifies TRICO, traditional bid-build delivery and USD 2,521,449.52 Contract Total; its expected-start field remains planning evidence only.