Port de Plaisance du Grand Large marine works

Participation
Not assessed
Project facts checked

SPAD concluded three separate Grand Large marina works contracts on 30 June 2026 with Eiffage Travaux Maritimes et Fluviaux, Atlantic Marine and Ramery Travaux Publics; each lot carries a 24-month planned period, but no dated notice to proceed or field mobilisation has been located

Project sources

Société Publique de l'Agglomération Dunkerquoise awarded three Port de Plaisance du Grand Large packages. Eiffage Travaux Maritimes et Fluviaux won Lot 1 marine civil works at EUR 3,739,243; Atlantic Marine won Lot 2 floating pontoons at EUR 2,083,000; and the Lot 3 winning tender, named as Ramery Travaux Publics in consortium with Montanier, was EUR 2,777,007. Those legal awards define the package map and 24-month planned periods, but they do not prove field mobilisation, identify Lot 3's declared lower-tier subcontractors or explain the difference between the three tender values and the notice-level total.

Official SPAD concept rendering of the Port de Plaisance du Grand Large Dunkerque marina basin, floating pontoons, protective structure and waterfront technical zone

S3D / SPAD; official Pointe des Alliés concept rendering, not a current contract drawing or construction-progress image

Location

France / Europe

Segment

Marinas, pontoons and berthing infrastructure

Phase

Award / Confirmed

Last checked

5 August 2026

Coverage

Related sectors

Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Société Publique de l'Agglomération Dunkerquoise (SPAD), acting on the Grand Large marina works
Delivery parties
Eiffage Travaux Maritimes et Fluviaux - Lot 1 marine civil works, EUR 3,739,243; six electronic submissions, Atlantic Marine SAS - Lot 2 floating pontoons, EUR 2,083,000; two electronic submissions, Ramery Travaux Publics - Lot 3 contract reference, EUR 2,777,007; winning tender named a consortium with Montanier and five electronic submissions, Unnamed Lot 3 subcontractors - the winning tender declares EUR 678,449 or 24% for subcontracting, but the cited award XML gives no company names, Lot 4 networks and electricity contractor - not established by the cited three-lot procedure
Contract route
SPAD published open procedure 47258-2026 on 22 January 2026 with a 27 March tender deadline. The wider operation was divided into four lots: this formal procedure covered Lots 1-3, while Lot 4 networks and electricity was to run separately under an adapted procedure. Award notice 542678-2026 records Lot 1 and Lot 2 award decisions on 15 June, Lot 3 on 30 June, and contract issue or conclusion on 30 June 2026 for all three.
Execution window
Each of Lots 1-3 carries a 24-month planned duration. The award notice does not publish a start date, notice to proceed, site-possession record, current programme, completion date or acceptance event. Counting 24 months from the 30 June contract date would be an inference, not an official delivery schedule.
Works package
Lot 1 covers removal of existing breakwater modules and unusable piles, new guide piles, new breakwater modules and equipment, a lifting basin, a collector-gangway access platform and acoustic monitoring. Lot 2 covers phased permanent pontoons, temporary removal and reinstatement, catways, six gangways including a utility gangway, safety equipment and relocation of the pilots' pontoon. Lot 3 covers earthworks, trenches, refuelling pontoon and networks, ducts, careening and storage areas, roads and pavements, lighting, fencing, access control, signage, waste facilities and associated equipment.
Marine interfaces
The live interface joins pile and wave-attenuation work, floating pontoons, six gangways, marina traffic, pilots' berthing, lifting and careening operations, fuel and utility services, water treatment, access control and environmental noise monitoring. The official Pointe des Alliés concept places these works inside a broader 450-berth marina and 10,000 m2 technical-zone plan, but that wider urban and waterfront programme is not the disclosed scope of the three contracts.
Commercial evidence boundary
The award XML provides a lot ledger but not a reconciled programme account. Lot-level payable amounts total EUR 8,599,250; the top-level notice amount is EUR 10,488,651. The XML contains no bridge between them. Lot 3 also declares EUR 678,449, or 24%, of subcontracting without naming the recipients. Montanier appears in the winning-tender reference as Ramery's consortium partner and should not be relabelled as the unnamed subcontractor. Payments, variations, final account and the Lot 4 award value remain undisclosed.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Lot 1 award

Marine civil works: piles, breakwater and lifting basin

Named party
Eiffage Travaux Maritimes et Fluviaux
Evidence status
Confirmed
Source position
TED records a EUR 3,739,243 winning tender, six electronic submissions, award on 15 June and contract conclusion on 30 June 2026. Source
Lot 2 award

Floating pontoons, catways and six gangways

Named party
Atlantic Marine SAS
Evidence status
Confirmed
Source position
TED records a EUR 2,083,000 winning tender, two electronic submissions, award on 15 June and contract conclusion on 30 June 2026. Source
Lot 3 award

Roads, refuelling and water treatment

Named party
Ramery Travaux Publics in consortium with Montanier
Evidence status
Confirmed
Source position
The winning tender reference names the Ramery-Montanier group at EUR 2,777,007 with five electronic submissions; the settled-contract reference names Ramery and is dated 30 June 2026. Source
Lot 3 lower tier

Declared subcontracting

Named party
Undisclosed subcontractors
Evidence status
Undisclosed
Source position
The award XML reports EUR 678,449 and 24% subcontracting but publishes no recipient names. Source
Separate procurement

Lot 4 networks and electricity

Named party
SPAD and an unverified contractor
Evidence status
Not evidenced
Source position
The contract notice says Lot 4 would be procured separately; the cited three-lot award does not identify its winner, value or status. Source
Commercial total

Notice-level and lot-level value reconciliation

Named party
SPAD
Evidence status
Confirmed
Source position
The award XML reports EUR 10,488,651 at notice level while the three winning tender values total EUR 8,599,250, leaving EUR 1,889,401 unexplained. Source
Physical delivery

Mobilisation, installation, testing and acceptance

Named party
SPAD and the three award groups
Evidence status
Not evidenced
Source position
Legal award and planned duration are the latest dated milestones; site mobilisation, installed works, testing and handover remain unrecorded.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

The three-lot award notice was published

The result disclosed winners, lot values, bidder counts and Lot 3 subcontracting while leaving mobilisation and the total-value reconciliation open.

Source

All three works contracts were concluded

Lot 1 went to Eiffage TMF, Lot 2 to Atlantic Marine and the Lot 3 winning tender named the Ramery-Montanier group; contract dates do not prove site start.

Source

SPAD opened the three-lot works competition

The notice separated marine civil works, floating pontoons and landside systems from a fourth networks-and-electricity procurement with its own award path.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dated site possession and lot-by-lot field mobilisation
  • Lot 4 networks and electricity award
  • Ramery-Montanier consortium roles and Lot 3 subcontractors
  • Guide-pile, breakwater, pontoon, catway and gangway suppliers
  • Marine plant, lifting-basin sequence and pilots' pontoon move
  • Acoustic, water-treatment and fuel-system controls
  • EUR 10.489 million notice total versus EUR 8.599 million lot-value reconciliation
  • Testing, owner acceptance, berth release and final account

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
5 August 2026
Cited sources
7

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 7