Project record

Cleveland Harbor 2026 maintenance dredging

Ryba Marine pumps dredged material from a scow into a Cleveland Harbor confined disposal facility in November 2020

U.S. Army photo by Jess Levenson, USACE Buffalo District

USACE Buffalo awarded DMYLES a USD 11.7 million contract on 9 April 2026 for approximately 250,000 cubic yards from Cleveland Harbor's upper Cuyahoga River channel across two planned windows. Mobilisation, first-window production, measured quantity, placement split and completion are not confirmed.

Project signal

Award in United States

Keep the 2026 package at award until USACE or another accountable owner source confirms physical execution. Read the May-June and October-November dates as planned production windows, then test actual mobilisation, measured volume, sediment route, post-dredge hydrography, and accepted channel condition against the separate near-term SPMF/CDF and long-term CHEERS capacity tracks.

Current status USD 11.7 million award confirmed; no 2026 field execution is documented Source confidence Confirmed

Location

United States / Americas

Segment

Port infrastructure

Status

USD 11.7 million award confirmed; no 2026 field execution is documented / Confirmed

Evidence reviewed

16 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
U.S. Army Corps of Engineers, Buffalo District
Delivery parties
DMYLES, Inc.
Contract route
USD 11.7 million federal maintenance dredging contract covering two execution windows
Execution window
15 May-30 June and 1 October-30 November 2026
Works package
Dredging of approximately 250,000 cubic yards from the upper Cuyahoga River section of Cleveland Harbor's federal navigation channel
Marine interfaces
Maintenance of 5.8 miles of federal Cuyahoga River channel plus one mile of Old River, annual upper-river shoaling, upland processing, beneficial use, confined disposal, and short- and long-term placement-capacity planning
Commercial read
The award is specific and funded, but the delivery question is wider than dredging volume: two seasonal windows must pass through a live sediment-routing system while SPMF capacity is extended, nearshore alternatives remain under assessment, and CHEERS remains a future programme rather than current placement capacity.
Next milestone
Accountable evidence of first-window mobilisation and measured production, including the actual material route and post-dredge survey; absent that evidence, retain award phase before the planned 1 October return.

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

DMYLES received the two-window maintenance award

USACE awarded DMYLES USD 11.7 million for approximately 250,000 cubic yards from the upper Cuyahoga River, with work planned for 15 May-30 June and 1 October-30 November. Award and planned dates do not establish mobilisation, production, placement, survey acceptance, or completion.

Read controlling source

USACE opened short-term placement scoping

The preliminary-assessment addendum evaluates limited open-water placement, CDF 12, the Port's SPMF, and littoral nourishment for future Cleveland material management. It is an alternatives and public-comment record, not a selected or authorised route for the 2026 DMYLES contract.

Read controlling source

The Port approved an SPMF capacity bridge through 2029

The Port board awarded a USD 4 million extension project to Mark Haynes Construction to keep the current repository usable until CHEERS is ready. The award establishes a capacity intervention, not completed construction or unlimited placement capacity.

Read controlling source

A separate prior-year DMYLES campaign was scheduled to start

USACE announced a USD 9 million 2025 contract for approximately 180,000 cubic yards from the lower Cuyahoga and CDF placement. USACE later reported 255,651 cubic yards removed in 2025; neither the earlier scope nor that result proves 2026 execution.

Read controlling source

The Port documented a split sediment route

The Port reported approximately 50,000 cubic yards hydraulically placed into the SPMF for processing and beneficial use and approximately 150,000 cubic yards routed to a silt basin. A separate 20,000-cubic-yard Cleveland-Cliffs dock campaign is excluded from the federal-channel total.

Read controlling source

USACE published the DMMP and EIS review plan

The review plan defines the technical and peer-review path for long-term dredged-material management. It is planning evidence and does not establish a final DMMP, approved CHEERS capacity, or a selected annual placement route.

Read controlling source

Delivery watch

Evidence needed next

Accountable evidence of first-window mobilisation and measured production, including the actual material route and post-dredge survey; absent that evidence, retain award phase before the planned 1 October return.

Decision watchpoints

  • Measured completion of the May-June dredging window
  • October mobilisation, production, and 30 November completion
  • Final volume split between upland processing and confined disposal
  • Remaining confined-disposal and beneficial-use capacity
  • Post-dredge hydrography and published federal-channel availability

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 16 July 2026 Sources in this record 10

Source record

The 14 April 2026 USACE release confirms the 9 April USD 11.7 million DMYLES award, approximately 250,000 cubic yards from the upper Cuyahoga, and planned 15 May-30 June and 1 October-30 November windows. It does not report mobilisation or first-window completion. USACE's January placement scoping evaluates limited open-water placement, CDF 12, the Port's SPMF, and littoral nourishment; scoping is not route approval. The October 2025 factsheet gives the 225,000-cubic-yard annual baseline and authorised channel geometry. Port records separately document the 2024 material split, the July 2025 SPMF extension award through 2029, and CHEERS as a design, permitting, and funding programme rather than available capacity. The prior 2025 DMYLES contract and its later-reported 255,651-cubic-yard result are historical performance context, not evidence for the 2026 package.

Phase: award. Evidence reviewed: 16 July 2026.

Project sources 10