Location
Democratic Republic of the Congo / Africa
Project record
Office of the Prime Minister of the Democratic Republic of the Congo
Construction of the Democratic Republic of the Congo's first deep-water container port is under way at Banana. DP World defines a 600-metre first-phase quay, a 30-hectare yard and 450,000 TEU of annual design capacity; Mota-Engil reports an approximately EUR 230 million phase-one contract with an estimated 24-month term. Published design-depth figures are not fully aligned: DP World's 2021 agreement release states an 18-metre draft, while British International Investment's 2024 investment release states 17.5 metres. DRC government statements targeted delivery and first vessel calls in 2026, but a May 2026 government update still called for acceleration and warned that local disruption could delay execution. No current primary record in the reviewed set confirms accepted berth geometry, completed terminal commissioning or commercial opening.
Democratic Republic of the Congo / Africa
Deep-water ports and container terminals
Phase-one marine and terminal works are under way; the DRC government was still pressing for acceleration in May 2026, so the previously stated 2026 delivery and first-vessel dates remain targets rather than evidence of accepted operation / Confirmed
15 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The Prime Minister's office recorded political concern about manoeuvres and slowdowns that could delay execution and renewed acceleration as a priority. It did not publish a revised completion date, quantified progress, accepted marine output, terminal readiness or an opening notice.
Read controlling sourceThe government visit confirmed construction activity, naval-base relocation, hydrological review at the Congo River mouth and anti-erosion works. The photographs also show dredged-material placement, but the record does not quantify dredging, formed area, achieved depth, quay completion or owner acceptance.
Read controlling sourceThe high-level meeting recorded an attributed delivery and first-call objective if execution remained in order. It is schedule evidence, not proof of marine completion, navigation release, terminal commissioning or a booked commercial service.
Read controlling sourceThe regulated notice recorded an approximately EUR 230 million contract and an estimated 24-month term for phase one. It does not define every marine subcontract, total development cost, accepted geometry, completion date or opening date.
Read controlling sourceThe up-to-USD 35 million commitment advanced the investment structure and published a 17.5-metre design-depth statement. Marine works were not awarded, DP World's 18-metre statement remained unreconciled, and no construction, acceptance or operating performance was established.
Read controlling sourceThe official record identifies early coastal-protection activity. Later phase-one contracting, revetment completion, dredging and reclamation quantities, shoreline acceptance and port completion remain outside that early activity record.
Read controlling sourceThe ceremony marked political and contractual launch after the collaboration agreement. It did not prove contractor mobilisation, physical marine production, package acceptance, terminal commissioning or operation.
Read controlling sourceThe agreement set the phased port-development structure, initial 600-metre quay, 30-hectare yard, 450,000-TEU design capacity and 18-metre draft statement. Agreement and design evidence are not construction, as-built geometry or operating capacity.
Read controlling sourceDelivery watch
Seek dated evidence for marine surveys and accepted berth geometry, platform and quay handover, equipment awards and installation, utilities and terminal-system commissioning, navigation and harbour-service approvals, customs and ISPS readiness, corridor and gate integration, trial vessel calls, first commercial service and repeat calls. Record any revised opening date without converting it into completion evidence.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerDP World's December 2021 final-agreement and February 2022 first-stone releases control the programme and ceremony baselines; the ceremony is not construction output. The DRC Prime Minister's May 2023 record controls the first reported rock-armour activity. DP World's March 2025 release controls contractor selection and the first-phase terminal frame, while Mota-Engil's regulated market notice controls the approximately EUR 230 million value and estimated 24-month term. BII's August 2024 release controls its up-to-USD 35 million minority investment, 17.5-metre draft statement and impact forecasts. DRC government records control the attributed 2026 target, September 2025 site activity and April 2026 acceleration warning. The current record does not establish dredging quantities, breakwater boundaries, percentage completion, accepted draft, opening or throughput.
Phase: construction. Evidence reviewed: 15 July 2026.