Jetty 3 at Fremantle Fishing Boat Harbour was replaced by Western Australia's Department of Transport with a modern floating pen system for 45 berths. Tenders WA records the site inside DOT409421RFT, a common design-and-construct contract awarded on 29 April 2022 to Global Trade Sales (Gambetta Holdings Pty Ltd), which the owner called GTS Australia. The official project page photographs demolition and new-pile installation in October 2022 and records completion in 2023. A January 2026 Transport WA article states that the Jetty 3 project cost AUD 4.6 million.
Project signal
Completed in Australia
Current statusTransport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade SalesSource confidenceConfirmed
Location
Australia / Asia Pacific
Segment
Marinas, pontoons and berthing infrastructure
Status
Transport WA records Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost; the works formed one site under the two-location DOT409421RFT contract awarded to Global Trade Sales / Confirmed
Last checked
8 August 2026
Coverage
Related sectors
Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Western Australia Department of Transport, now Department of Transport and Major Infrastructure
Delivery parties
Global Trade Sales (Gambetta Holdings Pty Ltd), referred to by the owner as GTS Australia - confirmed design-and-construct contractor under DOT409421RFT, Design, demolition, piling, pontoon, services and marine-plant lower tiers - no organization named in the reviewed records
Contract route
Tenders WA records an Open Advertisement one-off works contract with 14 submissions. DOT409421RFT started on 29 April 2022 and has a final expiry date of 21 December 2023. The current page publishes an original estimate of AUD 15,582,213, a revised estimate of AUD 14,464,405 and actual contract expenditure of AUD 14,448,283 for both project sites.
Execution window
The common contract ran from 29 April 2022 to 21 December 2023. Transport WA photographs demolition and new-pile installation in October 2022, planned most Fremantle work for mid to late 2023 and now records Jetty 3 completed in 2023. The cited sources do not publish a precise practical-completion date, reopening date or acceptance certificate.
Works package
At Fremantle, the contract covered demolition and removal of Jetty 3; design, supply and installation of a floating boat-pen system; piling; and power, water, firefighting and CCTV services. The owner states that the completed system accommodates 45 modern berths.
Marine interfaces
The replacement was delivered inside an operating fishing boat harbour serving recreational and commercial vessels. The public evidence confirms demolition, pile installation, floating pens and services, but does not disclose temporary moorings, construction-vessel spreads, pile quantities, pontoon manufacturer, service commissioning tests or the accepted as-built package.
Commercial evidence boundary
The January 2026 owner article gives AUD 4.6 million for Jetty 3, while the 2022-23 annual report estimated AUD 4.936 million and the 2021-22 report had estimated AUD 5.806 million. These dated project-cost statements are not site allocations from DOT409421RFT and should not be added to, subtracted from or used to reconcile the common contract without an owner cost ledger.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Common design-and-construct award
DOT409421RFT Fremantle Jetty 3 and Hillarys jetties A, F, G, H and J
Named party
Global Trade Sales (Gambetta Holdings Pty Ltd)
Status
Confirmed
Source position
Tenders WA records the open-advertisement award, 14 submissions, supplier, contract dates and combined value fields. Source
Fremantle physical scope
Jetty 3 demolition, floating pens, piles and services
Named party
Department of Transport and Global Trade Sales
Status
Confirmed
Source position
The official contract description and owner project page define the 45-berth floating replacement and service systems. Source
Field delivery
Old-jetty demolition and new-pile installation
Named party
Global Trade Sales and undisclosed lower tiers
Status
Confirmed
Source position
Transport WA's exact-project image and caption record demolition and pile installation in October 2022. Source
Project completion
Jetty 3 floating pen system
Named party
Department of Transport
Status
Confirmed
Source position
Transport WA states that work to upgrade Jetty 3 was completed in 2023. Source
Project cost
Fremantle Jetty 3 replacement
Named party
Department of Transport and Major Infrastructure
Status
Reported
Source position
A January 2026 owner article states a cost of AUD 4.6 million; it does not identify a DOT409421RFT schedule-of-prices allocation. Source
Lower-tier delivery chain
Design, demolition, piles, pontoons, services and marine plant
Named party
No organization disclosed
Status
Undisclosed
Source position
The combined-project workforce statements provide headcount context but no named subcontractor or site-level workshare.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Transport WA's exact-site imagery establishes demolition and pile-installation activity at Fremantle without identifying the marine plant, specialist suppliers or lower-tier companies.