Completed jetty cost record

Fremantle Jetty 3 records AUD 4.6m project cost

Published 8 August 2026 Publisher IMWO Region Asia Pacific Confidence Confirmed
Transport WA Fremantle Jetty 3 location plan for the proposed replacement

Transport WA via the Internet Archive; exact Fremantle Jetty 3 location plan for the proposed replacement, not an as-built plan or completion record

Transport WA records Fremantle Fishing Boat Harbour Jetty 3 completed in 2023 and later states an AUD 4.6 million project cost. The replacement delivered 45 floating berths after demolition and new-pile installation photographed in October 2022. Its design-and-construct award sits inside DOT409421RFT, a common contract covering both Fremantle and Hillarys.

Transport WA publishes the project-level AUD 4.6 million cost

Tenders WA publishes the common award, supplier, dates, competition and contract values. Transport WA publishes the exact Jetty 3 scope, October 2022 field activity, 2023 completion and AUD 4.6 million project statement. The 2022 workforce forecast spans both contract sites and names no lower-tier company.

Jetty 3 needs its own physical and commercial record

The completed asset has a clear location, scope, berth count, contractor and owner-reported project cost. The common contract values cover a second site at Hillarys and cannot supply a Fremantle schedule-of-prices allocation. Keeping the asset record distinct prevents the AUD 4.6 million statement from being mistaken for the executed contract share or added to the common expenditure.

Evidence conclusion

The common contract remains the governing commercial record

The AUD 4.6 million statement belongs to the completed Jetty 3 project. Tenders WA's AUD 15.582 million original estimate, AUD 14.464 million revised estimate and AUD 14.448 million actual expenditure belong to both contract sites. An executed site allocation, precise practical-completion date, acceptance certificate, as-built pile schedule and named lower tiers remain unpublished. The October 2022 field image establishes demolition and pile installation at the exact site, while the 2023 owner statement establishes completion only at year level.

Outstanding evidence

  • Jetty 3 practical-completion, reopening and owner-acceptance dates
  • Site-level final cost basis behind the AUD 4.6 million statement
  • Executed DOT409421RFT schedule of prices or owner allocation
  • As-built pile, pontoon, berth and services quantities
  • Named pontoon, piling, electrical, water, firefighting and CCTV lower tiers
  • Defect closeout, warranty and final-account records
  • Continued separation from the later Jetty 1 contract DOT411425