Mali's Landscape Restoration Project split the Dioro riverbank works into two signed lots under one national Request for Bids. Lot 1 covers cyclopean-concrete bank works and associated improvements; World Bank records allocate its USD 727,366.40 total equally between EKA SARL and Alternative BTP SA. Lot 2 covers the central riverbank section and rehabilitation of the port quay, with SENO BTP holding the USD 686,453.98 contract. The two disclosed awards total USD 1,413,820.38. The procurement plan published in April 2026 labels the parent package under implementation but does not prove field mobilisation, completed work or owner acceptance.
Project signal
Award in Mali
Current statusTwo works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been publishedSource confidenceConfirmed
Location
Mali / Africa
Segment
Inland river-port quay and bank rehabilitation
Status
Two works lots under ML-UGP-PRTD-477915-CW-RFB were signed in December 2025; the April 2026 procurement plan marks the package under implementation, but no lot-specific mobilisation, progress, completion or acceptance record has been published / Confirmed
Last checked
10 August 2026
Coverage
Related sectors
Inland river-port quay and bank rehabilitation is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Mali Landscape Restoration Project (PRTD-Mali), financed by the International Development Association
Delivery parties
EKA SARL - named Lot 1 supplier with USD 363,683.20 allocated by the World Bank award record, Alternative BTP SA - named Lot 1 supplier with USD 363,683.20 allocated by the World Bank award record, SENO BTP - Lot 2 contractor for the central riverbank section and port-quay rehabilitation, Supervision consultant, material suppliers, river plant and other lower tiers - not identified in the cited public records
Contract route
PRTD-Mali used an open national, post-review Request for Bids under reference ML-UGP-PRTD-477915-CW-RFB. The two official contract entries record Lot 2 signed on 11 December 2025 and Lot 1 signed on 12 December 2025. The procurement plan dated April 2026 gives a USD 1,492,537 package estimate, records no actual amount and marks the process under implementation.
Execution window
The procurement plan contains planned procurement and execution dates but no reliable lot-specific notice to proceed, actual site-start date or accepted completion date. The December contract signatures establish the commercial baseline only. Mobilisation, temporary works, river access, construction progress, practical completion and operational release remain unconfirmed.
Works package
Lot 1 is described as cyclopean-concrete bank development with related works. Lot 2 covers development of the central Dioro riverbank section and rehabilitation of the port quay. The cited public records do not disclose quay length, wall type, design levels, stone or concrete quantities, dredging, access-road limits, services, fendering, mooring hardware or issued-for-construction drawings.
Marine interfaces
The package joins bank stabilization to a working inland port edge on the Niger River system. Delivery will need to manage seasonal river levels, erosion control, temporary shoreline access, small-craft movements, quay interfaces and safe public access. Those are constructability considerations inferred from the asset type, not evidence of a published method statement or completed control measure.
Commercial evidence boundary
The signed award values are USD 727,366.40 for Lot 1 and USD 686,453.98 for Lot 2, totalling USD 1,413,820.38. The equal Lot 1 supplier allocations do not by themselves establish a joint venture, lead member or subcontract relationship. The procurement-plan estimate of USD 1,492,537 is a planning baseline, while its zero actual amount is not evidence that nothing has been paid. No variation, certified expenditure, final account or exchange-rate basis is public.
Contract and delivery chain
Named roles and open packages
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Lot 1 award
Cyclopean-concrete riverbank works and associated improvements
Named party
EKA SARL and Alternative BTP SA
Status
Confirmed
Source position
World Bank contract record 1887866 gives a USD 727,366.40 lot total and equal supplier allocations. Source
Lot 2 award
Central riverbank section and port-quay rehabilitation
Named party
SENO BTP
Status
Confirmed
Source position
World Bank contract record 1887867 gives a USD 686,453.98 signed works award to SENO BTP. Source
Procurement status
Two-lot Dioro bank-development package
Named party
PRTD-Mali
Status
Confirmed
Source position
The April 2026 procurement plan identifies the package estimate and labels the procurement process under implementation. Source
Physical delivery
Mobilisation, construction, inspection and acceptance
Named party
PRTD-Mali and the named lot suppliers
Status
Not evidenced
Source position
No cited public record supplies a lot-specific site start, measured progress, completion certificate or port-use release.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.