Inland Port Infrastructure
Dioro's two signed lots still stop short of a usable quay
IMWO artist's impression accompanying this evidence brief, depicting Dioro
Two December 2025 contracts now define Dioro's riverbank and port-quay package. EKA SARL and Alternative BTP SA share the recorded Lot 1 supplier amount for cyclopean-concrete bank works, while SENO BTP holds Lot 2 for the central bank section and quay rehabilitation. The signed total is USD 1,413,820.38, but the latest procurement plan supplies no actual amount or evidence of a usable quay.
One procurement package now has two priced delivery lots
World Bank contract data identifies the lot titles, parties, dates and values. The April 2026 procurement plan gives the package estimate and workflow status only; it is not evidence of mobilisation or completion. No cited source provides accepted physical quantities, an operating release or project-specific lower tiers.
The port interface sits inside the second lot
The contract records separate the bank-protection platform from the central section and port-quay interface. Sequencing, supervision and commercial closeout therefore depend on both lots: completion of a bank segment alone would leave the quay's small-craft safety unproven, while quay closeout still depends on adjacent erosion-control and access interfaces. Supervision, design geometry, quantities and construction plant remain undisclosed in the public record.
Evidence conclusion
Physical acceptance remains unverified
World Bank records confirm three suppliers, two signed lot values and the shared procurement reference. The evidence leaves the legal relationship between the two Lot 1 suppliers, field mobilisation, approved drawings, physical progress, final quantities and acceptance unresolved. The April 2026 plan's 'under implementation' label is a procurement-workflow signal, not a construction certificate. The USD 1,492,537 estimate, USD 1,413,820.38 signed aggregate and any future final account must remain separate figures.
Outstanding evidence
- Notices to proceed and field mobilisation for each lot
- Approved quay and bank-protection geometry and quantities
- Contractual relationship between the two Lot 1 suppliers
- Supervision appointment and named lower-tier suppliers
- Seasonal river, erosion, navigation and access controls
- Measured progress, variations and revised completion dates
- Practical completion, defects status and quay operating release
- Certified expenditure and final account
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 5
- Dioro Lot 1 contract award record 1887866 World Bank Contract Awards, Contract signed 12 December 2025; checked 10 August 2026
- Dioro Lot 2 contract award record 1887867 World Bank Contract Awards, Contract signed 11 December 2025; checked 10 August 2026
- Consolidated contract query for ML-UGP-PRTD-477915-CW-RFB World Bank Contract Awards, Current API record checked 10 August 2026
- P177041 procurement plan World Bank, 13 April 2026
- P177041 RESILAND Mali Landscape Restoration Project World Bank Projects and Operations, Current project page checked 10 August 2026