Project record

Ruwais LNG marine access and export terminal

ADNOC rendering of the planned Ruwais LNG plant and marine export berth with an LNG carrier alongside

ADNOC; official Ruwais LNG project rendering

NMDC Group's marine package for Ruwais LNG covers about 15 million cubic metres of dredging along a 5-kilometre, 245-metre-wide access channel and the installation of navigation aids. An ADNOC Petroleum Ports Authority notice dated 22 February 2025 put the work into phased, round-the-clock execution and mapped the channel, two offshore disposal sites, environmental buoys and a silt curtain. ADNOC still described the overall LNG project as under development in July 2026.

Project signal

Construction in UAE

Current status Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published Source confidence Confirmed

Location

UAE / Middle East

Segment

Deep-water ports and energy terminals

Status

Ruwais LNG remains under development for 2028 commercial operations; a February 2025 port notice placed the access-channel dredging in phased 24-hour execution, but no final marine acceptance record has been published / Confirmed

Last checked

20 July 2026

Coverage

Related sectors

Deep-water ports and energy terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Abu Dhabi National Oil Company (ADNOC)
Delivery parties
NMDC Group for marine dredging and navigation aids, Technip Energies, JGC Corporation and NMDC Energy for the separate LNG plant EPC
Contract route
ADNOC awarded NMDC Group a marine dredging contract worth more than USD 200 million in August 2024. The marine package is separate from the approximately USD 5.5 billion plant EPC awarded to the Technip Energies, JGC and NMDC Energy joint venture.
Execution window
The Petroleum Ports Authority notice dated 22 February 2025 described phased dredging operations running 24 hours a day. ADNOC reported in November 2025 that construction, contractor mobilisation and site works were on track for commissioning by the end of 2028, and in July 2026 continued to describe the project as under development with commercial operations scheduled for 2028.
Works package
The published marine contract covers removal of approximately 15 million cubic metres over a 5-kilometre channel with a 245-metre width, plus navigation aids. The port notice adds the field-control picture: an access-channel dredging area, two offshore disposal sites, marker and environmental buoys, a silt curtain and phased 24-hour operations.
Marine interfaces
The access channel, disposal route, environmental controls and navigation aids must connect a new LNG export berth to the existing Ruwais and Jebel Dhanna port environment. That interface links dredger traffic, disposal management, hydrographic control, temporary markers, permanent navigation aids, berth and jetty readiness, port-authority operating controls and the plant's commissioning sequence.
Commercial evidence boundary
Long-term LNG sales now cover 90% of the planned 9.6 mtpa capacity, but offtake does not demonstrate marine readiness. The project record still needs an accepted channel and berth, commissioned aids to navigation, final disposal and environmental close-out, and operating approval before the 2028 commercial target can be treated as an executable vessel-service date.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

ADNOC kept the 2028 commercial target and reported 90% of capacity committed

The latest owner update confirms commercial cover and continued development. It does not report access-channel acceptance, navigation-aid commissioning or berth readiness.

Source

The Petroleum Ports Authority issued the RLNG dredging operations notice

The notice moved the marine record beyond award by identifying phased 24-hour execution, the access-channel work area, two offshore disposal sites and environmental controls.

Source

NMDC Group received the marine dredging contract

The award defined an approximately 15 million cubic metre, 5-kilometre channel package worth more than USD 200 million, including navigation aids.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dredging completion and final reconciled quantity
  • Accepted post-dredge hydrographic survey and channel depth
  • Offshore disposal-site and environmental-monitoring close-out
  • Permanent navigation-aid installation and commissioning
  • Export jetty, berth pocket and mooring-system handover
  • Port-authority marine operating approval
  • Alignment between marine acceptance and plant commissioning
  • First LNG carrier call and start of commercial operations in 2028

Reporting status

Construction, confirmed confidence

Last checked 20 July 2026 across 7 cited sources. The dated timeline above carries the project events.

Last checked 20 July 2026 Cited sources 7