Location
Ghana / Africa
Project record
Prime Meridian Docks; existing Takoradi quayside context, not the future floating dock
Project Shiprite is a USD 137 million ship-repair development inside Ghana's Port of Takoradi. Its marine scope includes a 200-metre jetty, about 300,000 m3 of rock dredging, reclaimed working land and a 13,500-tonne lift-capacity floating dock. PIDG joined the investor group on 1 June 2026 with USD 9.7 million in equity and shareholder lending. Public disclosures still stop short of financial close, a named civil EPC or dredging contractor, a dock builder and a dated start on site.
Ghana / Africa
Port infrastructure
PIDG capital committed; financial close and construction start still to be confirmed / Confirmed
20 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
PIDG committed USD 9.7 million in equity and shareholder lending and said the investment closed a final funding gap. The release says the transaction can proceed to financial close and construction; it does not report close, notice to proceed or site mobilisation.
Read controlling sourceAfreximbank said the agreement secured the full commitment of the capital providers. The later PIDG funding-gap statement shows that this 2024 commitment milestone did not by itself establish financial close or physical construction.
Read controlling sourceThe approval fixed the USD 137 million project basis, 25-year concession and principal marine scope. It was a lender approval, not a works award or mobilisation notice.
Read controlling sourceThe environmental study requires a site-specific dredging management plan and assigns construction monitoring to the EPC contractor under PMD and engineering oversight. It supplies the control framework but not evidence that the works started.
Read controlling sourceDelivery watch
A dated financial-close or first-drawdown notice followed by the civil EPC and dock-builder appointments, notice to proceed, baseline hydrographic survey, dredging-management approval and evidence of dredger, piling or reclamation mobilisation at Takoradi.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerAfDB approved USD 23.04 million in June 2023 and set out the main marine scope. AfDB and Afreximbank followed in June 2024 with a USD 94 million senior facility agreement, described at the time as the full capital commitment. Interocean called the project well underway in September 2024, although its article records a partner site visit rather than a dated marine work front. It also gives 18,000 m2 of reclaimed land, against 30,000 m2 in the lender releases. PIDG's 1 June 2026 announcement says its USD 9.7 million investment filled the final gap and cleared the way to financial close and construction. AfDB's portal still lists the project as ongoing with a May 2027 planned completion date. Its zero-disbursement field may be stale and should be checked with the lenders rather than read as a project-status verdict.
Phase: financing. Evidence reviewed: 20 July 2026.