Project record
Prime Meridian Docks; existing Takoradi quayside context, not the future floating dock
Project Shiprite is a USD 137 million ship-repair development inside Ghana's Port of Takoradi. Its marine scope includes a 200-metre jetty, about 300,000 m3 of rock dredging, reclaimed working land and a 13,500-tonne lift-capacity floating dock. PIDG joined the investor group on 1 June 2026 with USD 9.7 million in equity and shareholder lending. Public disclosures still stop short of financial close, a named civil EPC or dredging contractor, a dock builder and a dated start on site.
Ghana / Africa
Port infrastructure
PIDG capital committed; financial close and construction start still to be confirmed / Confirmed
20 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogPIDG committed USD 9.7 million in equity and shareholder lending and said the investment closed a final funding gap. The release says the transaction can proceed to financial close and construction; it does not report close, notice to proceed or site mobilisation.
SourceAfreximbank said the agreement secured the full commitment of the capital providers. The later PIDG funding-gap statement shows that this 2024 commitment milestone did not by itself establish financial close or physical construction.
SourceThe approval fixed the USD 137 million project basis, 25-year concession and principal marine scope. It was a lender approval, not a works award or mobilisation notice.
SourceThe environmental study requires a site-specific dredging management plan and assigns construction monitoring to the EPC contractor under PMD and engineering oversight. It supplies the control framework but not evidence that the works started.
SourceEvidence gap