Location
Bangladesh / Asia Pacific
Project record
World Bank completion reporting confirms three fish landing stations and two fish markets completed by project close on 28 November 2025; five other sites in the original 10-site package could not start because of land-tenure disputes
Bangladesh's Department of Fisheries awarded package WD 17 for upgrading and modernizing ten existing fish landing stations and fish markets to Starlite Services Ltd. and Monalisa Construction Ltd. World Bank completion reporting later confirms that only five sites proceeded: three fish landing stations and two fish markets were completed, while five other sites could not start because private, multi-owner land-tenure disputes were not resolved.
Bangladesh / Asia Pacific
Port infrastructure
Completed / Confirmed
3 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe final report records three fish landing stations and two fish markets completed by the closed operation, replacing the original ten-site title with the achieved output.
SourceWorld Bank mission reporting recorded three landing stations near 65% and two markets near 75%, while five sites could not start because private, multi-owner land-tenure disputes remained unresolved.
SourceWorld Bank award data names Starlite Services Ltd. and Monalisa Construction Ltd. under the ten-site package without publishing their shares, site split or subcontractors.
SourceEvidence gap