Project record

Sitra Wharf Berths 5 and 6 liquid-cargo enhancement

Participation
Not assessed
Project facts checked

Bahrain Tender Board's March 2026 monthly report records a BHD 10,987,831 award to NASS Contracting for Sitra Wharf tender T78534; no award date, contract signature, mobilisation or installed work is published

Project sources

Bapco Refining tendered construction at New Island Wharf Berths 5 and 6 to increase Sitra Port Terminal's liquid-cargo handling capacity and accommodate larger hydrocarbon cargoes. Three accepted bids opened on 17 March 2025. Bahrain Tender Board's March 2026 monthly award report later names NASS Contracting Co. W.L.L. at BHD 10,987,831. The monthly report fixes the award recipient and reported amount, but not the legal award date, contract signature, notice to proceed, physical start or current progress.

Bapco tanker berth alongside Sitra Wharf in NASS's official Berths 3 and 4 ship-impact protection project image

Nass Corporation; exact NASS predecessor project at Sitra Wharf Berths 3 and 4, not T78534 Berths 5 and 6 construction or current progress

Location

Bahrain / Middle East

Segment

Liquid-cargo terminal berth enhancement

Phase

Award / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Liquid-cargo terminal berth enhancement is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Bapco Refining
Delivery parties
NASS Contracting Co. W.L.L. - confirmed award recipient in Bahrain Tender Board's March 2026 monthly report, Marine, structural, mechanical, piping, loading-system, electrical, instrumentation, diving, survey and supply lower tiers - no organization disclosed
Contract route
Bapco Refining used a selected LOCAL GCC request for proposals under tender 26/2025/BTB (T78534). Three accepted bids opened on 17 March 2025: Al Hassanain at BHD 16,283,057, NASS at BHD 12,286,739 and Mohammed Jalal option 2 at BHD 19,869,000; the BHD 0 display for option 1 is not a priced alternative. The later monthly award report names NASS at BHD 10,987,831. Tender Board cautions that opened prices remain subject to evaluation and the lowest bidder is not necessarily awarded.
Execution window
The published Tender Board records provide no contract-signing date, notice to proceed, duration, site-possession date, shutdown window, mobilisation, first physical operation, completion target or acceptance date for T78534. The March 2026 report period end is an observation date only, not the award or signing date.
Works package
The tender description places construction at New Island Wharf Berths 5 and 6 within Bapco Refining's Sitra Port Terminal and states the objective as increasing liquid-cargo handling capacity for larger hydrocarbon cargoes. It does not publish a bill of quantities, issued design, berth geometry, structural components, loading-arm scope, fender or mooring schedule, pipeline tie-ins, dredging, utilities, control systems or commissioning tests.
Marine interfaces
The work sits inside an operating export terminal used by Bapco businesses. Berth availability, vessel and terminal continuity, hazardous-area access, live product systems, marine plant, navigation coordination, structural and mechanical tie-ins, shutdowns, testing and return to service are relevant operating interfaces. No cited record confirms how these responsibilities are packaged or assigned.
Commercial evidence boundary
The Tender Board opened-bids page records NASS at BHD 12,286,739. The later award report records BHD 10,987,831, a numerical difference of BHD 1,298,908. Public evidence does not explain whether scope alignment, clarification, arithmetic correction, negotiation, exclusions or another mechanism caused the difference. No source establishes contract amendments, payment, contingency, final value, savings or lower-tier values.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Main works award

Sitra Wharf Enhancement Project construction works, tender T78534

Named party
NASS Contracting Co. W.L.L.
Evidence status
Confirmed
Source position
Bahrain Tender Board's March 2026 monthly report names NASS and reports BHD 10,987,831. Source
Tender scope

Construction at New Island Wharf Berths 5 and 6 to increase liquid-cargo capacity

Named party
Bapco Refining
Evidence status
Confirmed
Source position
The official opened-bids page defines the berth boundary and capacity objective without publishing detailed quantities. Source
Opened competition

Three accepted LOCAL GCC RFP bids

Named party
Al Hassanain, NASS and Mohammed Jalal
Evidence status
Confirmed
Source position
Tender Board records the three bidder names and opened prices on 17 March 2025; accepted opening status is not an award. Source
Commercial reconciliation

NASS opened bid versus reported award

Named party
Bapco Refining and NASS Contracting Co. W.L.L.
Evidence status
Reported
Source position
The source values differ by BHD 1,298,908, but no reviewed record explains the cause or establishes a final account.
Operating-terminal context

Sitra Wharf product-export interface

Named party
Bapco Refining and Bapco Gas
Evidence status
Confirmed
Source position
Bapco states that products are shipped globally via Sitra Wharf; that operating context does not prove T78534 mobilisation. Source
Lower-tier delivery chain

Marine, structural, mechanical, piping, electrical, instrumentation, survey, diving and supply packages

Named party
No lower-tier organization named
Evidence status
Undisclosed
Source position
Neither the opened-bids page nor the monthly award report identifies subcontractors, suppliers, workshare or plant.
Physical execution and acceptance

Mobilisation, construction, testing and return to service

Named party
Bapco Refining and NASS Contracting Co. W.L.L.
Evidence status
Not evidenced
Source position
The award record does not establish notice to proceed, site possession, installed quantities, commissioning or owner acceptance.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Monthly report observes the NASS award

The report fixes the award recipient and BHD 10,987,831 amount; its month-end date is not the legal award, signing or mobilisation date.

Source

Three accepted bids open

NASS is the lowest displayed priced bid at BHD 12,286,739, while Tender Board explicitly warns that opening status does not determine award.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Legal award date, contract signature and notice to proceed
  • Accepted scope, berth geometry, quantities and design responsibility
  • Programme, berth outages, shutdowns and operating continuity
  • Structural, piping, loading, mooring, fender and control-system boundaries
  • Marine plant, survey, diving and temporary works
  • Named subcontractors, suppliers and workshare
  • Explanation for the BHD 1,298,908 opened-bid to award difference
  • Progress, commissioning, return to service, final value and owner acceptance

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
8 August 2026
Cited sources
6

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 6