Project record

Bangladesh Bay Terminal marine infrastructure

Bay Terminal layout showing the offshore breakwater, planned container terminals, basin and access channel west of Chattogram

Chittagong Port Authority / World Bank revised ESIA, Figure 3-3; planning layout, not construction progress

Chittagong Port Authority is developing the common marine infrastructure for Bay Terminal with World Bank financing. The public design baseline combines a 6-kilometre offshore breakwater, dredging for a 6.6-kilometre access route, port basin and entrance works, navigation aids and VTMS integration. The latest World Bank implementation report says the financing is effective and key studies are nearing completion, but physical works have not commenced.

Project signal

Design in Bangladesh

Treat Bay Terminal as a financed project in design, not as an awarded US$827 million marine contract or an active construction site. The breakwater and dredging package structure is still being tested, while the separate PPP process for container-terminal development cannot start its RFP until the feasibility study and transaction-structure report are approved.

Current status IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started Source confidence Confirmed

Location

Bangladesh / Asia Pacific

Segment

Port infrastructure

Status

IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started / Confirmed

Evidence reviewed

19 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Chittagong Port Authority (CPA), Government of Bangladesh
Delivery parties
No marine works contractor identified in reviewed official sources, Transaction adviser engaged for the separate terminal-operator PPP
Contract route
IDA-financed international competitive procurement using World Bank documents and rated criteria. The 2024 procurement strategy groups breakwater construction and capital dredging in a preliminary US$827 million line, but says the scope is likely to be split after market survey and PPSD finalisation. A separate PPP route will recruit international terminal operator(s).
Execution window
World Bank financing closes on 30 June 2031; package tender, award, mobilisation and construction dates remain unconfirmed
Works package
A 6 km rubble-mound breakwater on the offshore sandbar, dredging of a 5 km basin reach and roughly 1.6 km entrance reach for a 6.6 km access route, an expected capital-dredging volume close to 30 million m3, navigation aids and VTMS updates
Marine interfaces
Offshore breakwater design, sandbar stabilisation, a live approach to Chattogram, basin and entrance-channel dredging, sediment monitoring, navigation systems and the handover boundary between publicly funded common marine works and privately developed container terminals
Commercial read
The World Bank's US$650 million financing is a project envelope, not a marine-works award. The US$827 million figure is a preliminary procurement-plan estimate for breakwater and capital dredging, the US$5 million line is for navigation aids and VTMS, and the US$830 million indicator is a future private-investment target for at least one terminal. None is a signed construction contract.
Next milestone
Final feasibility, design and PPSD decisions, followed by the first official prequalification or tender notice defining whether breakwater, capital dredging and any initial maintenance period are procured together or separately

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

Latest implementation report kept physical works at pre-start

The World Bank recorded effective financing and studies nearing completion, while marine works remained pre-start and the terminal PPP RFP awaited feasibility and transaction-structure approval.

Read controlling source

IDA financing became effective

The three IDA credits moved from signature to effective status. Effectiveness released the financing framework but did not award or start a marine-works contract.

Read controlling source

World Bank approved the Bay Terminal financing

Approval established the US$650 million project envelope and common marine-infrastructure objective, including the breakwater and channel works. It was not a construction award.

Read controlling source

Delivery watch

Evidence needed next

Final feasibility, design and PPSD decisions, followed by the first official prequalification or tender notice defining whether breakwater, capital dredging and any initial maintenance period are procured together or separately

Decision watchpoints

  • Completion and approval of marine feasibility, detailed design and PPSD
  • Final split between breakwater, capital dredging and initial maintenance dredging
  • Prequalification and rated-criteria tender documents for each marine package
  • Design depth, dredge prism, measured quantity and sediment-management route
  • Breakwater foundation, sandbar stabilisation and scour-protection requirements
  • Navigation aids, VTMS integration and live-traffic controls
  • Contract awards, notice to proceed and identifiable mobilisation
  • Baseline and post-dredge hydrography, breakwater acceptance and navigation release
  • Interface agreement with the future private terminal operator

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 19 July 2026 Sources in this record 6

Source record

The World Bank approved US$650 million for Bay Terminal in June 2024 and signed the financing in April 2025. The 16 January 2026 implementation report records effectiveness on 8 December 2025, says works have not commenced, and keeps the 6.6-kilometre access-channel outcome at zero while studies near completion. The appraisal document defines a 6-kilometre rubble-mound breakwater, a 5-kilometre basin reach, a roughly 1.6-kilometre entrance reach, an expected capital-dredging volume close to 30 million cubic metres, and navigation-system work. Its procurement table is preliminary: the US$827 million breakwater and capital-dredging line may be divided, and the dredging contract may include three years of performance-based maintenance. The revised ESIA supplies the project layout and environmental baseline, not construction evidence.

Phase: design. Evidence reviewed: 19 July 2026.

Project sources 6