Chittagong Port Authority is developing the common marine infrastructure for Bay Terminal with World Bank financing. The public design baseline combines a 6-kilometre offshore breakwater, dredging for a 6.6-kilometre access route, port basin and entrance works, navigation aids and VTMS integration. The latest World Bank implementation report says the financing is effective and key studies are nearing completion, but physical works have not commenced.
Project signal
Design in Bangladesh
Current statusIDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not startedSource confidenceConfirmed
Location
Bangladesh / Asia Pacific
Segment
Port infrastructure
Status
IDA financing effective since 8 December 2025; marine studies are nearing completion, but works and the terminal-operator RFP have not started / Confirmed
Last checked
19 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Chittagong Port Authority (CPA), Government of Bangladesh
Delivery parties
No marine works contractor identified in reviewed official sources, Transaction adviser engaged for the separate terminal-operator PPP
Contract route
IDA-financed international competitive procurement using World Bank documents and rated criteria. The 2024 procurement strategy groups breakwater construction and capital dredging in a preliminary US$827 million line, but says the scope is likely to be split after market survey and PPSD finalisation. A separate PPP route will recruit international terminal operator(s).
Execution window
World Bank financing closes on 30 June 2031; package tender, award, mobilisation and construction dates remain unconfirmed
Works package
A 6 km rubble-mound breakwater on the offshore sandbar, dredging of a 5 km basin reach and roughly 1.6 km entrance reach for a 6.6 km access route, an expected capital-dredging volume close to 30 million m3, navigation aids and VTMS updates
Marine interfaces
Offshore breakwater design, sandbar stabilisation, a live approach to Chattogram, basin and entrance-channel dredging, sediment monitoring, navigation systems and the handover boundary between publicly funded common marine works and privately developed container terminals
Commercial evidence boundary
The World Bank's US$650 million financing is a project envelope, not a marine-works award. The US$827 million figure is a preliminary procurement-plan estimate for breakwater and capital dredging, the US$5 million line is for navigation aids and VTMS, and the US$830 million indicator is a future private-investment target for at least one terminal. None is a signed construction contract.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Latest implementation report kept physical works at pre-start
The World Bank recorded effective financing and studies nearing completion, while marine works remained pre-start and the terminal PPP RFP awaited feasibility and transaction-structure approval.
The three IDA credits moved from signature to effective status. Effectiveness released the financing framework but did not award or start a marine-works contract.
Approval established the US$650 million project envelope and common marine-infrastructure objective, including the breakwater and channel works. It was not a construction award.