Location
Nigeria / Africa
Project record
MSC has taken a 45-year sub-concession for a new container terminal at Snake Island Port in Lagos and finalized an EPC contract with ITB Nigeria and DEME. The stated design has a 910-metre quay, a 30-hectare yard and initial dredging to -16.5 m chart datum, with provision for a later -18 m depth.
Nigeria / Africa
Deep-water ports and container terminals
MSC signed a 45-year sub-concession and finalized the ITB/DEME EPC on 11 March 2026; the reviewed project sources do not record mobilisation / Confirmed
18 July 2026
Coverage
Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe container-terminal package now has a 45-year commercial structure, named EPC parties and defined design geometry. The announcement does not establish a work start or operating date.
SourceNPA placed the wider port development on an 85-hectare site and used a USD 1 billion development figure. No EPC value, construction programme or physical progress record was included.
SourceThe approval established a 45-year, USD 974.19 million multipurpose-port framework for Nigerdock and SIIFZ. ICRC said projects would still proceed to commercial close before commencement.
SourceEvidence gap