Curtin Maritime's hybrid clamshell dredge DB Avalon is removing approximately 1.46 million cubic yards from Baltimore Harbor approach channels under the 2026 maintenance programme. Material is loaded into scows and taken to the Cox Creek Dredged Material Containment Facility.
Project signal
Construction in United States
Current statusCurtin Maritime's DB Avalon was operating in the Patapsco River on 16 June 2026Source confidenceConfirmed
Location
United States / Americas
Segment
Port infrastructure
Status
Curtin Maritime's DB Avalon was operating in the Patapsco River on 16 June 2026 / Confirmed
Last checked
18 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
U.S. Army Corps of Engineers, Baltimore District, with Maryland Port Administration
Delivery parties
Curtin Maritime
Contract route
Competitively awarded federal maintenance-dredging contract executed by Curtin Maritime. The current 2026 story publishes the 1.46-million-cubic-yard scope but not a contract value; USD 229 million is a broader fiscal-year appropriation and the USD 33.5 million award belongs to the preceding fiscal-year package.
Execution window
Winter through late spring 2026, with DB Avalon operations observed on 16 June 2026.
Works package
Mechanical clamshell dredging of approximately 1.46 million cubic yards of fine-grained silt and clay from Baltimore Harbor approach channels, loading into scows and transport to the Cox Creek Dredged Material Containment Facility
Marine interfaces
Hybrid-powered clamshell dredging in the Patapsco River, 24-hour rotating operations, scow loading, tug movements, Cox Creek offloading and maintenance of authorized 50-foot channels that are 800 to 1,000 feet wide
Commercial evidence boundary
The current contractor, plant, quantity, channel geometry and Cox Creek route are public. The current contract value is not. The broader USD 229 million fiscal-year appropriation, the preceding USD 33.5 million fiscal-year award and STAR's separate remediation and reuse programme should not be merged into one contract value or delivery claim.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
USACE field reporting and exact-site photographs confirm active clamshell excavation and scow loading under the current 1.46-million-cubic-yard package. They do not establish final production or accepted channel condition.
USACE published the current approach-channel quantity and geometry
Baltimore District identified approximately 1.46 million cubic yards before spring 2026 and restated the 50-foot authorized depth and 800-to-1,000-foot channel widths.
Port Commission minutes record a five-year plan to reclaim 1.2 million cubic yards of Cox Creek capacity. The planned recovery remains separate from dredged material received in 2026 and from verified reuse output.