Location
Ireland / Europe
Project record
Dublin Port is building a new quay at Berth 52 East and a 290-metre open RoRo jetty at Berth 53. The €128.7065 million contract covers piled marine structures, a double-tier linkspan, automated mooring, scour protection, marine furniture and landside systems for ferries up to 240 metres long.
Ireland / Europe
Port infrastructure
Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open / Confirmed
18 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The result identifies Wills Bros and €128.7065 million excluding VAT. It also records 25 April 2024 as the contract date, so publication in 2026 is a procurement-disclosure event rather than a new award.
Read controlling sourceDublin Port reported the 290-metre open jetty, nine dolphins, Berth 52 East extension, linkspan and landside systems, while fixing seasonal limits for river piling and dredging.
Read controlling sourceDublin Port recorded physical piling and more than 70 Wills Bros staff on the works. This moves the package beyond award without establishing completed foundations or a usable berth.
Read controlling sourceThe €73.8 million grant supports two inter-dependent berths totalling 572 metres, double-tier linkspans and shore-power provision for RoRo vessels up to 240 metres.
Read controlling sourceDelivery watch
Confirm the accepted foundation and deck sequence, then follow completed dolphins, quay continuity, scour and dredging records, linkspan and mooring installation, hydrographic and load-test acceptance, berth handover and first sustained ferry service.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerDublin Port's 2026 harbour notice controls the present work-zone boundary and says construction east of Berth 53 runs from May 2024 to January 2027. The 2026 yearbook and May 2025 owner update define the 290-metre jetty, nine dolphins, Berth 52 East extension, linkspan and environmental windows. Wills Bros supplies the pile, sheet, concrete and precast quantities. TED controls the €128.7065 million award value and Wills Bros identity, but its 20 April 2026 publication date must not be presented as the award date because the notice records contract conclusion on 25 April 2024. The first marine piles in August 2024 prove execution had started; they do not prove completed foundations, accepted berths, commissioned systems or ferry service.
Phase: construction. Evidence reviewed: 18 July 2026.