Location
Ireland / Europe
Project record
Dublin Port is building a new quay at Berth 52 East and a 290-metre open RoRo jetty at Berth 53. The €128.7065 million contract covers piled marine structures, a double-tier linkspan, automated mooring, scour protection, marine furniture and landside systems for ferries up to 240 metres long.
Ireland / Europe
Port infrastructure
Marine construction is active; the 2026 harbour notice keeps the buoyed work zone in place through January 2027, while berth acceptance and service release remain open / Confirmed
18 July 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe result identifies Wills Bros and €128.7065 million excluding VAT. It also records 25 April 2024 as the contract date, so publication in 2026 is a procurement-disclosure event rather than a new award.
SourceDublin Port reported the 290-metre open jetty, nine dolphins, Berth 52 East extension, linkspan and landside systems, while fixing seasonal limits for river piling and dredging.
SourceDublin Port recorded physical piling and more than 70 Wills Bros staff on the works. This moves the package beyond award without establishing completed foundations or a usable berth.
SourceThe €73.8 million grant supports two inter-dependent berths totalling 572 metres, double-tier linkspans and shore-power provision for RoRo vessels up to 240 metres.
SourceEvidence gap