Ports & Terminals
Dublin Port's MP2 package carries 232 tubular piles
Dublin Port's €128.7065 million Berths 52/53 contract is well past award. Marine piling began in August 2024, the 2026 harbour notice keeps a buoyed work zone active through January 2027, and Wills Bros lists 232 tubular piles, 57 combi-wall piles and 145 CFA piles across the package.
What changed
Dublin Port's 2026 notice defines an active work zone through January 2027 and identifies the crane barges, tugs, multicat, workboats and landing craft at the site. The 2026 yearbook and May 2025 update define the berth geometry and environmental windows. Wills Bros supplies the package quantities. TED identifies the contractor and €128.7065 million value, but its publication date is not the award date. Completed piling, accepted deck and linkspan systems, formal handover and operating service have not been reported.
Why it matters
Berth 53 is a 290-metre open jetty with nine dolphins, a double-tier linkspan and automated mooring for ferries up to 240 metres. Berth 52 East extends the reclaimed edge into the river and ties the two structures together. The berth can enter service only after the foundations, deck, scour protection, marine furniture, linkspan, power and navigation interfaces are accepted as one system.
Decision read
What remains open
This is live marine construction, not a 2026 contract award. TED published the result in April 2026 but dates the contract to 25 April 2024; Dublin Port recorded first piles four months later. The current harbour notice confirms the workfront and marine plant, while leaving completed quantities, hydrographic acceptance, berth handover and ferry service unreported.
Next watchpoints
- Accepted tubular, combi-wall, CFA and sheet-pile quantities
- Nine dolphins, open-jetty deck and Berth 52 East structural tie
- Scour protection, marine furniture and seasonal dredging
- Linkspan, bridge, automated mooring and shore-power interfaces
- Hydrographic, structural and operational acceptance
- Ferry trials, berth handover and first sustained service
Knowledge context
Related knowledge topics
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Sources used 6
- Notice 32/2026 - MP2 Construction Works Dublin Port Company Harbour Master, Current 2026 notice reviewed 18 July 2026
- Dublin Port Yearbook 2026 - Delivering on MP2 Dublin Port Company, 2026 edition reviewed 18 July 2026
- Significant progress at MP2 Berths 52 and 53 Dublin Port Company, 27 May 2025
- First marine piles at the Berth 53 jetty Dublin Port Company, 30 August 2024
- MP2 Works at Berths 52 and 53 contract award result Tenders Electronic Daily, 20 April 2026
- MP2 Berths 52 and 53 project quantities Wills Bros, Current project page reviewed 18 July 2026
Corrections and methodology
Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.