Project record
IMWO artist's impression of the published Manangareza river-port station rehabilitation scope
PIC3's Manangareza river-port station package at Toamasina has moved from an August 2025 national tender to a signed works contract. ECH BTP holds 031/T/PIC3/2025, signed on 28 November 2025 for USD 1,272,815.07. Separate World Bank entries name Bureau d'Etudes Da Vinci SARL and Cabinet d'Architecture A&C for both the design study and construction supervision. The owner tender describes one indivisible lot, while the pre-award consultant scope calls for improved shoreside facilities and separation of passenger and goods traffic. Cited materials leave the notice to proceed, site mobilisation, construction progress, completion and owner acceptance unverified.
Madagascar / Africa
Inland river-port station and passenger-cargo terminal rehabilitation
ECH BTP signed the USD 1,272,815.07 works contract on 28 November 2025; public records also name the design and supervision consultant, but no notice to proceed, mobilisation, measured progress, completion or acceptance has been located / Confirmed
10 August 2026
Coverage
Inland river-port station and passenger-cargo terminal rehabilitation is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe post-review administrative field follows the works signature, but it supplies no notice to proceed, site mobilisation, measured progress or acceptance evidence.
SourceThe signed award fixes ECH BTP as prime contractor under 031/T/PIC3/2025 and establishes the USD 1,272,815.07 committed commercial baseline.
SourceClosure of the national competition preserved one indivisible rehabilitation and development lot, without identifying bids, evaluation scores or a selected supplier at that stage.
SourceEvidence gap