Location
Syria / Middle East
Project record
Tartous has progressed from a May 2025 memorandum to a signed 30-year BOT concession, formal operator handover, harbour-tug service, and the first of three mobile harbour cranes. Channel, basin, and berth dredging, achieved depths, quay acceptance, and the wider terminal upgrade remain open delivery gates.
Syria / Middle East
Port infrastructure
Operations active; modernisation equipment mobilising / Confirmed
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
The first crane reached Tartous and two more were scheduled by August. Arrival proves equipment mobilisation, not commissioning of all three cranes or the expected 40% cargo-capacity increase.
Read controlling sourceFormal handover moved the concession into operation and added a 50-tonne-bollard-pull harbour tug. DP World was still surveying infrastructure and quay readiness and described channel, basin, and berth dredging as an immediate focus, not completed work.
Read controlling sourceThe signed concession replaced the preliminary memorandum with a 30-year development-and-operation structure and an USD 800 million programme. It did not identify marine package awards, contractors, quantities, target depths, or completion dates.
Read controlling sourceThe memorandum established an USD 800 million investment intent for development, management, and operation of a multi-purpose terminal. It was an early commercial milestone rather than proof of concession execution, operator handover, or physical works.
Read controlling sourceDelivery watch
Confirm the remaining crane arrivals and commissioning, then identify dredging and quay packages, marine plant, target and achieved depths, rehabilitation acceptance, and sustained vessel-performance evidence.
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerSANA records a 16 May 2025 memorandum between the General Authority for Land and Sea Ports and DP World for an USD 800 million multi-purpose-terminal investment; that preliminary instrument was not the operating concession. DP World records the signed 30-year Build-Operate-Transfer concession on 13 July, covering new port infrastructure, cargo-handling equipment, digital systems, and container and general-cargo terminal improvement. Its 12 November operations update confirms formal handover, the 50-tonne-bollard-pull harbour tug Al Fath entering service, infrastructure and quay-readiness surveys, and an immediate plan to dredge access channels, basins, and berths to target design depths. SANA separately attributes the first-phase scope to the port authority, corroborating infrastructure and equipment upgrades, deepening, handling-machinery replacement, and digital systems without claiming completion. DP World's 1 July 2026 update says the first of three new mobile harbour cranes arrived on 29 June, the other two were scheduled by August, and the three-crane package was expected to increase cargo-handling capacity by about 40% once operational. The first crane is verified mobilisation; completed dredging, achieved design depths, accepted quay rehabilitation, all-crane commissioning, and realised capacity gains remain unconfirmed.
Phase: early works. Evidence reviewed: 16 July 2026.