Project record
DERM Group signed the USD 20.16 million berth electrical-power works contract in October 2024; the planned June 2026 end has passed without public completion or acceptance evidence
Tanzania Ports Authority signed World Bank project contract TZ-TPA-310413-CW-RFB with DERM Group Company Limited on 31 October 2024 for design, supply, installation and commissioning of electrical power at Dar es Salaam Port's berths 1-7 and RoRo berth. The World Bank contract record reports USD 20,159,532.34, and the July 2025 implementation report said installation works were ongoing. The planned implementation window ended in June 2026, but no cited source confirms commissioning, acceptance or defects closeout.
Tanzania / Africa
Port berth electrical systems and commissioning
Construction / Confirmed
5 August 2026
Coverage
Port berth electrical systems and commissioning is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe project implementation report said procurement of the electrical power-supply installation contract was complete and works were ongoing; it did not report energisation, commissioning or acceptance.
SourceThe World Bank supplier dataset named DERM Group Company Limited and reported USD 20,159,532.34 for design, supply, installation and commissioning at berths 1-7 and the RoRo berth.
SourceThe World Bank allowed a 24-month installation and supervision window, long equipment lead times and live-port commissioning, while recognizing that defects obligations could continue beyond closing.
SourceEvidence gap