Dar es Salaam's berth electrical award now needs commissioning proof
World Bank; Dar es Salaam Port context, not berth electrical commissioning evidence
DERM Group Company Limited signed a USD 20,159,532.34 World Bank-financed works contract on 31 October 2024 for design, supply, installation and commissioning of electrical power at Dar es Salaam's berths 1-7 and RoRo berth. A July 2025 World Bank report said installation works were ongoing. The June 2026 programme target has now passed, while public sources still lack energisation, integrated load testing, acceptance, defects commencement and confirmation of the proposed Ilala Substation connection.
A signed electrical package sits beyond its planned end date
World Bank contract 1808970 controls DERM's award, signature date, value and procurement method. The restructuring paper controls the planned implementation window, equipment lead time, live-port sequence, defects period and possible Ilala connection. The November 2024 implementation report separates completed civil works from electrical procurement; the July 2025 report says installation works were ongoing. No cited source confirms energisation or acceptance after the June 2026 target. The World Bank aerial is port context, not electrical-progress evidence.
Live-port commissioning carries different risks from civil completion
The port's civil narrative can obscure the unfinished systems boundary. Deepening and strengthening of berths 1-7 and the RoRo terminal, plus channel and turning-basin dredging, were reported complete by September 2024. DERM's later electrical package is separate. Berth availability alone does not prove that cables, transformers, switchgear, protection, earthing and upstream supply have passed operational commissioning.
Evidence conclusion
Civil readiness and electrical acceptance remain separate gates
The restructuring paper anticipated at least eight months for imported equipment and at least one year for installation, testing and commissioning around operating berths. It also allowed the 12-month defects period to extend beyond World Bank closing. A possible Ilala-to-port connection was described as a variation, leaving the upstream boundary commercially important. Public evidence still needs to identify supervision, equipment manufacturers, subcontractors, outage windows, energisation and accepted test results.
Outstanding evidence
- Energisation and integrated commissioning certificates
- Ilala Substation connection and variation status
- Transformer, switchgear and cable manufacturers
- Supervision and installation subcontract chain
- Defects period, final value and operating performance
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 7
- World Bank contract 1808970 for TZ-TPA-310413-CW-RFB World Bank Projects and Operations API, Contract signed 31 October 2024; record reviewed 5 August 2026
- Contract awards in investment project financing dataset, including TZ-TPA-310413-CW-RFB World Bank Finances One, Data current 4 August 2026
- Dar es Salaam Maritime Gateway Project P150496 World Bank, Current project record reviewed 4 August 2026
- P150496 restructuring paper World Bank, 21 August 2024
- P150496 implementation status and results report World Bank, Archived 13 July 2025
- P150496 implementation status and results report World Bank, Archived 19 November 2024
- Striving to Become the Regional Port of Choice World Bank, 25 January 2022