Location
Saudi Arabia / Middle East
Project record
USAspending records USD 400,172,871.91 obligated and exercised across 28 transactions through 7 July 2026; current performance end 8 March 2027
USACE's MMSC IOC facilities contract at King Abdulaziz Naval Base stands at USD 400,172,871.91 obligated and exercised after 28 transactions through 7 July 2026. The latest USD 45,102.95 action relocates a ring main unit. The original USD 319,535,250 design-build award covers wharf, pier, maintenance, fueling and utility facilities for Saudi Arabia's four-ship MMSC programme. The all-options value is USD 503,225,000.91 and the current contract period ends on 8 March 2027.
IMWO original editorial diagram, based on USAspending award and complete transaction ledger
Saudi Arabia / Middle East
Naval base wharf and fleet-support facilities
Construction / Confirmed
24 October 2026
Coverage
Naval base wharf and fleet-support facilities is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe USD 45,102.95 supplemental agreement takes the obligated/exercised value to USD 400,172,871.91 and all-options value to USD 503,225,000.91. The description records an electrical interface change; delivery status requires installation and testing evidence.
SourceThe USD 621,683.28 modification adds pump-house chiller and HVAC work. A00017 dated 7 July is the later transaction in the current ledger.
SourceThe USD 176,585.25 change exposes an active marine-to-shore utility interface. Its placement does not establish installation, testing or acceptance of the connected utility system.
SourceA zero-dollar modification changes paving and delivery administration. The current award period now ends on 8 March 2027, without a published facility-acceptance date.
SourceThe USD 29 million modification expands the shore-side support boundary beyond the original award description and adds a separate training-facility acceptance requirement.
SourceThe USD 15,602,632.04 reduction shows that gross additions cannot be read as simple project growth without the full transaction ledger.
SourceThe USD 40,812,851.40 modification establishes exercised fuel-system scope without identifying lower-tier installers, installed quantities, testing records or commissioning status.
SourceThe transaction description records a 42-day access-delay extension with a zero-dollar action. It identifies a programme adjustment alongside the priced scope account.
SourceThe USD 29,029,950.25 modification is the first recorded post-award increase and confirms option exercise without disclosing the package's physical delivery status.
SourceAICI-Archirodon JV LLC receives the USD 319,535,250 firm-fixed-price award after two bids, with Saudi FMS funds obligated at award.
SourceEvidence gap
Request filters award_id CONT_AWD_W912ER23C0002_9700_-NONE-_-NONE-, page 1, limit 5000, action_date ascending; 28 results, no next page.