Project record

Hillarys Boat Harbour jetties A, F, G, H and J replacement

Completed floating jetties and central walkway at Hillarys Boat Harbour shown in Transport WA's 2023-24 annual report

Transport WA; exact completed Hillarys Boat Harbour jetty-upgrade image from the 2023-24 annual report, page 61, showing the completed project

The final stage of the Hillarys Boat Harbour jetties A, F, G, H and J replacement was completed by Western Australia's Department of Transport in April 2024. The project demolished and replaced five end-of-life jetties with low-maintenance floating infrastructure connected to a realigned 3.5-metre-wide central walkway and accommodating 115 pens. Tenders WA places the works under DOT409421RFT with Global Trade Sales (Gambetta Holdings Pty Ltd). The 2023-24 annual report describes the project as AUD 10 million and records approximately 320 tonnes of steel piles, 51 tonnes of aluminium pontoon frames and 1,985 square metres of pontoons.

Project signal

Completed in Australia

Current status Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract Source confidence Confirmed

Location

Australia / Asia Pacific

Segment

Marinas, pontoons and berthing infrastructure

Status

Transport WA records the final stage completed in April 2024 as an AUD 10 million project, delivering five replacement floating jetties and 115 pens under the common DOT409421RFT contract / Confirmed

Last checked

8 August 2026

Coverage

Related sectors

Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Western Australia Department of Transport, now Department of Transport and Major Infrastructure
Delivery parties
Global Trade Sales (Gambetta Holdings Pty Ltd), referred to by the owner as GTS Australia - confirmed design-and-construct contractor under DOT409421RFT, WA floating-module, fendering and aluminium-frame suppliers - local manufacture confirmed but organizations not named, Piling, services, demolition and other lower tiers - organizations not named in the reviewed records
Contract route
Tenders WA records DOT409421RFT as an Open Advertisement one-off works contract with 14 submissions, awarded on 29 April 2022 and carrying a final expiry date of 21 December 2023. The contract combined Hillarys with Fremantle Jetty 3 and currently publishes AUD 15,582,213 original estimate, AUD 14,464,405 revised estimate and AUD 14,448,283 actual expenditure.
Execution window
The common contract period ended on 21 December 2023. Transport WA's annual report states that the Hillarys final stage completed in April 2024. The difference between the contract expiry field and the final-stage completion statement is an evidence boundary; public records do not explain whether it reflects staged completion, closeout, defects, owner work or contract administration.
Works package
The Hillarys site scope comprised demolition and removal of jetties A, F, G, H and J; a realigned 3.5-metre-wide central floating walkway; design, supply and installation of low-maintenance floating boat-pen systems; piling; power, water, firefighting and CCTV services; and capacity for 115 pens.
Marine interfaces
The replacement had to preserve penholder access and improve pedestrian movement for Rottnest Island ferry passengers and service vehicles inside an active harbour. The completed system combines piles, pontoons, fendering, aluminium frames, services and the central walkway, but public sources do not expose staging drawings, temporary access, pile installation methods, commissioning procedures or as-built service records.
Commercial evidence boundary
The 2023-24 annual report calls Hillarys an AUD 10 million project and says 84% of contract spend was in metropolitan WA, with the balance interstate and overseas. The 2022-23 annual report estimated total capital cost at AUD 10.014 million, up from AUD 9.464 million in earlier reports. These project and localisation fields cannot be used to allocate or reconstruct the common contract's final expenditure.

Contract and delivery chain

Named roles and open packages

Named appointments are shown against the workstream they cover. Unallocated packages remain open until a project source identifies the responsible party.

Common design-and-construct award

DOT409421RFT Hillarys jetties and Fremantle Jetty 3

Named party
Global Trade Sales (Gambetta Holdings Pty Ltd)
Status
Confirmed
Source position
Tenders WA records the open-advertisement award, 14 submissions, supplier, contract dates and combined value fields. Source
Hillarys physical scope

Jetties A, F, G, H and J, central walkway, piles, pontoons and services

Named party
Department of Transport and Global Trade Sales
Status
Confirmed
Source position
The contract record and June 2022 government release define the five-jetty replacement, 3.5-metre walkway and 115-pen outcome. Source
Local manufacturing

Floating modules, fendering and aluminium frames

Named party
Unnamed Western Australian suppliers
Status
Confirmed
Source position
The 2023-24 annual report states these components were 100% manufactured in WA and the aluminium came from WA and other Australian mills. Source
Installed quantities

Piles, aluminium frames and pontoons

Named party
Global Trade Sales and undisclosed suppliers
Status
Reported
Source position
The owner reports about 320 tonnes of steel piles, 51 tonnes of aluminium frames and 1,985 square metres of pontoons. Source
Completion

Final Hillarys jetty-replacement stage

Named party
Department of Transport
Status
Confirmed
Source position
The 2023-24 annual report states that the final stage completed in April 2024. Source
Workforce and lower tiers

Subcontract personnel and specialist suppliers

Named party
Organizations not disclosed
Status
Reported
Source position
The annual report records 18 subcontractor personnel including four apprentices and trainees; this does not identify 18 companies or their workshare.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

Hillarys final jetty-replacement stage completed

The owner records completion of the AUD 10 million project and publishes installed quantities, local-manufacturing outcomes, geographic spend and workforce facts.

Source

Estimated total capital cost reaches AUD 10.014 million

The 2022-23 annual report updates the project-level estimate to AUD 10.014 million without changing the common contract's separately published commercial fields.

Source

Two-site upgrade programme announced

The WA Government describes the Hillarys 3.5-metre walkway, five replacement jetties and 115-pen capacity under a rounded AUD 14 million common award.

Source

DOT409421RFT common contract awarded

Global Trade Sales receives the common two-site design-and-construct contract after an open competition that attracted 14 submissions from the market.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Explanation of the December 2023 contract expiry to April 2024 final-stage completion interval
  • Hillarys practical-completion and owner-acceptance documents
  • Site-level final cost and relationship to the rounded AUD 10 million statement
  • Names of WA pontoon, fendering and aluminium-frame manufacturers
  • Piling, demolition, electrical, water, firefighting and CCTV lower tiers
  • As-built pile, pontoon, berth and walkway quantities
  • Commissioning, defect closeout and warranty records

Reporting status

Completed, confirmed confidence

Last checked 8 August 2026 across 5 cited sources. The dated timeline above carries the project events.