Project record

Port of Santos 16 m channel deepening

Aerial view along the Port of Santos navigation channel, berths and terminals

Autoridade Portuaria de Santos; channel context published with the contract announcement, not mobilisation evidence

The Santos Port Authority has signed a five-year contract with Jan De Nul do Brasil to deepen the port navigation channel from 15 metres to a 16-metre DHN design depth. The integrated scope covers environmental licensing, basic and detailed design, capital dredging and two years of maintenance at the new design profile.

Project signal

Award in Brazil

Use the 12 June signature as the contract event, not as evidence that Jan De Nul has mobilised or that 16 metres is available to shipping. The current 15-metre maintenance cycle, DTA's separate rock-removal package, this capital-dredging contract and the proposed 25-year channel concession each require their own scope, survey and acceptance record.

Current status Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead Source confidence Confirmed

Location

Brazil / Americas

Segment

Port infrastructure

Status

Jan De Nul contract signed on 12 June 2026; official mobilisation, production and acceptance evidence remain ahead / Confirmed

Evidence reviewed

19 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Autoridade Portuaria de Santos (APS)
Delivery parties
Jan De Nul do Brasil Dragagem Ltda.
Contract route
Integrated electronic RLE 51/2025, Lot 1; APS approved Jan De Nul's offer after the tender review and signed the contract on 12 June 2026
Execution window
Five-year contract; the signed scope includes maintenance of the achieved 16-metre design profile for two years
Works package
Environmental licensing, basic and detailed design, deepening of the organised port navigation channel to a 16.00 m DHN design depth, and two years of maintenance dredging at the new profile
Marine interfaces
A 24.6-kilometre estuarine access channel, existing 15-metre maintenance operations, hydrographic controls, ocean disposal, separate rock-removal works, live vessel traffic and the future operating boundary of a proposed channel concession
Commercial read
APS and the Ministry of Ports and Airports describe the signed package as R$617.9 million, while APS executive-board minutes record approval of Jan De Nul's R$619,780,813.76 offer. The executed contract should control any final commercial comparison. Neither figure is the proposed concession investment of R$688 million.
Next milestone
Published work order or mobilisation notice, followed by licensing closure, accepted designs, baseline hydrography, dredging production, disposal records, post-dredge survey, navigation release and the start of the two-year maintenance period

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

APS signed the 16-metre deepening contract

Jan De Nul became the named contractor for the integrated licensing, design, capital-dredging and two-year maintenance scope. Signature did not establish mobilisation or achieved channel depth.

Read controlling source

APS approved Jan De Nul's Lot 1 offer

The executive board approved RLE 51/2025 and recorded the integrated package boundary and R$619,780,813.76 offer. Later public announcements describe the signed package as R$617.9 million, leaving the executed contract as the controlling commercial document.

Read controlling source

Delivery watch

Evidence needed next

Published work order or mobilisation notice, followed by licensing closure, accepted designs, baseline hydrography, dredging production, disposal records, post-dredge survey, navigation release and the start of the two-year maintenance period

Decision watchpoints

  • Formal work order and identifiable Jan De Nul mobilisation
  • Environmental licensing and closure of basic and detailed design
  • Interface with DTA's licensed rock-removal package
  • Baseline hydrography, target geometry and live-navigation controls
  • Dredging plant, measured production and ocean-disposal records
  • Authority acceptance of the surveyed 16-metre design profile after dredging
  • Operational draft or navigation release following physical acceptance
  • Start, performance and close-out of the two-year maintenance period
  • Handover boundary with any future access-channel concession

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 19 July 2026 Sources in this record 6

Source record

APS's 15 June release confirms the 12 June signature, Jan De Nul, five-year term, 16-metre objective and two years of maintenance. APS executive-board minutes identify RLE 51/2025, the integrated licensing and design scope, and the approved offer of R$619,780,813.76. MPor reports the package at R$617.9 million. The current APS dredging page controls the 24.6-kilometre, 15-metre channel baseline and the use of pre- and post-dredge hydrography. DTA's rock-removal contract and Ibama installation licence are separate enabling works. ANTAQ's open consultation concerns a separate proposed 25-year channel concession and does not establish transfer, award or operation. Jan De Nul mobilisation, dredged quantity, achieved depth, hydrographic acceptance and navigation release under the new contract are not confirmed.

Phase: award. Evidence reviewed: 19 July 2026.

Project sources 6