Location
India / Asia Pacific
Project record
Ramayapatnam Phase I was reported 52.95% complete against a INR 4,929.39 crore whole-port baseline on 4 April 2025 and remained officially under construction in February 2026. DEME's 16 June award is a later capital-deepening package for the harbour basin, turning circle, four berth pockets, and reclamation pumping; neither the whole-port percentage nor the award proves dredging mobilisation or accepted 15.5-metre access.
India / Asia Pacific
Port infrastructure
Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed / Confirmed
16 July 2026
Controlled taxonomy
The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.
Knowledge context
Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.
Project anatomy
Material change register
Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.
Navayuga awarded DEME capital deepening of the harbour basin, turning circle and four berth pockets, using a cutter suction dredger and onshore pumping for reclamation. The award does not establish mobilisation, dredged quantity, accepted depth or Phase I completion.
Read controlling sourceThe Railways ministry said RPDCL was developing the approximately 5.5-kilometre Ramayapatnam-to-Tettu connection under the Gati-Shakti Multi-Modal Cargo Terminal Policy and that work on the serving-station yard was at an advanced stage. It did not provide a completion date or establish completed rail access and cargo-evacuation readiness.
Read controlling sourceThe Ministry of Ports, Shipping and Waterways listed Ramayapatnam among four Andhra Pradesh ports under construction. This is a portfolio-status confirmation, not a package percentage, completion date or operating approval.
Read controlling sourceA Lok Sabha answer recorded the INR 4,929.39 crore port under implementation at 52.95% and described 34.04 MMTPA Phase I capacity. The percentage predates the DEME award by more than a year and cannot be used as dredging-package progress.
Read controlling sourceParliament listed INR 409.05 crore for the north breakwater, INR 12.59 crore for fire-fighting and navigational aids, and INR 34.35 crore for VTMS among Andhra Pradesh proposals. The ministry requested restructuring and alternative funding exploration; the list is not award or completion evidence.
Read controlling sourceThe SPSR Nellore district event register records initiation of the greenfield Ramayapatnam Port. It establishes the start boundary for the wider programme, not the later DEME package or completion of any marine element.
Read controlling sourceThe Ministry of Environment, Forest and Climate Change granted environmental and coastal-regulation-zone clearance for Phase I subject to project-specific and standard conditions. Clearance enabled the programme but did not award works, approve every later design change or prove construction acceptance.
Read controlling sourceDelivery watch
Named dredger and support-spread mobilisation, start of production and reclamation pumping, and a current owner-issued baseline for breakwaters, berths, navigation systems, and Phase I completion
This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.
Read featured analysis Review methodology Submit stronger evidence or a correction Open project trackerThe 17 February 2022 environmental and CRZ clearance established the Phase I port boundary before the district recorded project initiation on 20 July 2022. Xbloc documents December 2022 armour-unit casting and August 2023 placement for a 1,350-metre north breakwater and 3,730-metre south breakwater; CWPRS later confirmed hydraulic-stability testing for the breakwater sections. Parliament recorded proposed, not approved, funding items for the north breakwater, navigation aids, and VTMS in July 2024. A 4 April 2025 government answer reported the INR 4,929.39 crore port under implementation at 52.95% with 34.04 MMTPA Phase I capacity; that is the latest reviewed quantitative whole-port baseline. The government still listed Ramayapatnam under construction on 13 February 2026. On 27 March 2026 the Railways ministry said RPDCL was developing the approximately 5.5-kilometre Tettu connection under Gati-Shakti policy and that work on the serving-station yard was at an advanced stage; it did not report a completion date or completed port-rail access. DEME's 16 June 2026 release then established a separate capital-deepening award covering the basin, turning circle, four berth pockets, cutter-suction execution, onshore reclamation pumping, an approximately 15.5-metre design draft, and up to EUR 50 million for DEME's share. DEME mobilisation, production, completion hydrography, navigation-system acceptance and port handover have not been reported.
Phase: award. Evidence reviewed: 16 July 2026.