Project record

Ramayapatnam Port capital deepening works

Aerial view of Ramayapatnam Port's forming harbour basin and two breakwaters on the Bay of Bengal

Xbloc / Holcim Coastal

Ramayapatnam Phase I was reported 52.95% complete against a INR 4,929.39 crore whole-port baseline on 4 April 2025 and remained officially under construction in February 2026. DEME's 16 June award is a later capital-deepening package for the harbour basin, turning circle, four berth pockets, and reclamation pumping; neither the whole-port percentage nor the award proves dredging mobilisation or accepted 15.5-metre access.

Project signal

Award in India

Separate three evidence layers: wider Phase I port construction, the June 2026 DEME capital-deepening award, and the later navigation-and-terminal acceptance chain. The 52.95% figure applies to the whole port at the April 2025 reporting point, not to DEME's later package. Award does not prove plant arrival, dredged quantity, reclaimed formation, hydrographic acceptance, berth readiness, or usable draft.

Current status Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed Source confidence Confirmed

Location

India / Asia Pacific

Segment

Port infrastructure

Status

Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed / Confirmed

Evidence reviewed

16 July 2026

Controlled taxonomy

Related sectors

The detailed segment above is the primary work classification. These broader sector links connect the project to related delivery and market research.

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Project anatomy

Scope, counterparties, and execution logic

Client / authority
Navayuga Engineering Company Limited for the DEME package; Andhra Pradesh Maritime Board for the wider port
Delivery parties
DEME, Navayuga Engineering Company Limited / Auro Infra Private Limited joint venture for wider port works
Contract route
Greenfield non-major port under Andhra Pradesh Maritime Board delivery, with wider port works by the Navayuga-Auro joint venture and a separately awarded capital-deepening package from Navayuga to DEME
Execution window
No execution timing is stated for the DEME package; the reviewed February 2026 government record confirms the wider port remained under construction
Works package
DEME capital deepening of the harbour basin, turning circle, and four berth pockets, with cutter-suction-dredger production and onshore pumping for reclamation; wider Phase I includes two breakwaters, berths, navigation systems, and road and rail interfaces
Marine interfaces
Cutter-suction dredging, reclamation containment and formation, 1,350-metre north and 3,700-metre south breakwaters, berth pockets, turning circle, completion hydrography, aids, VTMS, and Panamax access
Commercial read
DEME's share is valued at up to EUR 50 million. It is a later package inside a port reported at INR 4,929.39 crore and 52.95% whole-port progress in April 2025; the values and percentages have different scopes and dates and must not be combined.
Next milestone
Named dredger and support-spread mobilisation, start of production and reclamation pumping, and a current owner-issued baseline for breakwaters, berths, navigation systems, and Phase I completion

Material change register

What changed, when, and what it proves

Only source-bound events that alter phase, scope, counterparties, delivery, completion, commissioning, or acceptance are listed. A change can advance the record without proving the next gate.

DEME received the capital-deepening package

Navayuga awarded DEME capital deepening of the harbour basin, turning circle and four berth pockets, using a cutter suction dredger and onshore pumping for reclamation. The award does not establish mobilisation, dredged quantity, accepted depth or Phase I completion.

Read controlling source

The Tettu serving-station yard reached an advanced stage

The Railways ministry said RPDCL was developing the approximately 5.5-kilometre Ramayapatnam-to-Tettu connection under the Gati-Shakti Multi-Modal Cargo Terminal Policy and that work on the serving-station yard was at an advanced stage. It did not provide a completion date or establish completed rail access and cargo-evacuation readiness.

Read controlling source

The port remained officially under construction

The Ministry of Ports, Shipping and Waterways listed Ramayapatnam among four Andhra Pradesh ports under construction. This is a portfolio-status confirmation, not a package percentage, completion date or operating approval.

Read controlling source

Government reported 52.95% whole-port progress

A Lok Sabha answer recorded the INR 4,929.39 crore port under implementation at 52.95% and described 34.04 MMTPA Phase I capacity. The percentage predates the DEME award by more than a year and cannot be used as dredging-package progress.

Read controlling source

North-breakwater, navigation-aid and VTMS funding remained proposals

Parliament listed INR 409.05 crore for the north breakwater, INR 12.59 crore for fire-fighting and navigational aids, and INR 34.35 crore for VTMS among Andhra Pradesh proposals. The ministry requested restructuring and alternative funding exploration; the list is not award or completion evidence.

Read controlling source

Andhra Pradesh recorded initiation of the greenfield port

The SPSR Nellore district event register records initiation of the greenfield Ramayapatnam Port. It establishes the start boundary for the wider programme, not the later DEME package or completion of any marine element.

Read controlling source

Phase I received environmental and CRZ clearance

The Ministry of Environment, Forest and Climate Change granted environmental and coastal-regulation-zone clearance for Phase I subject to project-specific and standard conditions. Clearance enabled the programme but did not award works, approve every later design change or prove construction acceptance.

Read controlling source

Delivery watch

Evidence needed next

Named dredger and support-spread mobilisation, start of production and reclamation pumping, and a current owner-issued baseline for breakwaters, berths, navigation systems, and Phase I completion

Decision watchpoints

  • Cutter-suction-dredger mobilisation and execution schedule
  • Harbour-basin, turning-circle, and berth-pocket quantities
  • Onshore pumping, reclamation containment, settlement, and ground performance
  • Completion hydrography and accepted navigation depth
  • North and south breakwater completion and armour acceptance
  • Aids, VTMS, rail interface, berth readiness, port handover, and first vessel access

Project availability status

This public project page is a tracked market record rather than a tender notice, contractual commitment, or commercial instruction. Use the status, confidence label, evidence-review date, and source note together when judging how much weight to place on the signal.

Read featured analysis Review methodology Submit stronger evidence or a correction Open project tracker

Record control

Evidence reviewed date is not a project-event date.

IMWO changes phase, participants, scope, completion, or acceptance wording only when a dated source establishes the change. The review date records when the evidence set was checked; it does not claim that physical work changed on that date.

Evidence reviewed 16 July 2026 Sources in this record 12

Source record

The 17 February 2022 environmental and CRZ clearance established the Phase I port boundary before the district recorded project initiation on 20 July 2022. Xbloc documents December 2022 armour-unit casting and August 2023 placement for a 1,350-metre north breakwater and 3,730-metre south breakwater; CWPRS later confirmed hydraulic-stability testing for the breakwater sections. Parliament recorded proposed, not approved, funding items for the north breakwater, navigation aids, and VTMS in July 2024. A 4 April 2025 government answer reported the INR 4,929.39 crore port under implementation at 52.95% with 34.04 MMTPA Phase I capacity; that is the latest reviewed quantitative whole-port baseline. The government still listed Ramayapatnam under construction on 13 February 2026. On 27 March 2026 the Railways ministry said RPDCL was developing the approximately 5.5-kilometre Tettu connection under Gati-Shakti policy and that work on the serving-station yard was at an advanced stage; it did not report a completion date or completed port-rail access. DEME's 16 June 2026 release then established a separate capital-deepening award covering the basin, turning circle, four berth pockets, cutter-suction execution, onshore reclamation pumping, an approximately 15.5-metre design draft, and up to EUR 50 million for DEME's share. DEME mobilisation, production, completion hydrography, navigation-system acceptance and port handover have not been reported.

Phase: award. Evidence reviewed: 16 July 2026.

Project sources 12