Ramayapatnam Phase I was reported 52.95% complete against a INR 4,929.39 crore whole-port baseline on 4 April 2025 and remained officially under construction in February 2026. DEME's 16 June award is a later capital-deepening package for the harbour basin, turning circle, four berth pockets, and reclamation pumping; neither the whole-port percentage nor the award proves dredging mobilisation or accepted 15.5-metre access.
Project signal
Award in India
Current statusGreenfield port under construction; capital-deepening package awarded, mobilisation unconfirmedSource confidenceConfirmed
Location
India / Asia Pacific
Segment
Port infrastructure
Status
Greenfield port under construction; capital-deepening package awarded, mobilisation unconfirmed / Confirmed
Last checked
16 July 2026
Coverage
Related sectors
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Navayuga Engineering Company Limited for the DEME package; Andhra Pradesh Maritime Board for the wider port
Delivery parties
DEME, Navayuga Engineering Company Limited / Auro Infra Private Limited joint venture for wider port works
Contract route
Greenfield non-major port under Andhra Pradesh Maritime Board delivery, with wider port works by the Navayuga-Auro joint venture and a separately awarded capital-deepening package from Navayuga to DEME
Execution window
No execution timing is stated for the DEME package; the reviewed February 2026 government record confirms the wider port remained under construction
Works package
DEME capital deepening of the harbour basin, turning circle, and four berth pockets, with cutter-suction-dredger production and onshore pumping for reclamation; wider Phase I includes two breakwaters, berths, navigation systems, and road and rail interfaces
Marine interfaces
Cutter-suction dredging, reclamation containment and formation, 1,350-metre north and 3,700-metre south breakwaters, berth pockets, turning circle, completion hydrography, aids, VTMS, and Panamax access
Commercial evidence boundary
DEME's share is valued at up to EUR 50 million. It is a later package inside a port reported at INR 4,929.39 crore and 52.95% whole-port progress in April 2025; the values and percentages have different scopes and dates and must not be combined.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Navayuga awarded DEME capital deepening of the harbour basin, turning circle and four berth pockets, using a cutter suction dredger and onshore pumping for reclamation. The award does not establish mobilisation, dredged quantity, accepted depth or Phase I completion.
The Tettu serving-station yard reached an advanced stage
The Railways ministry said RPDCL was developing the approximately 5.5-kilometre Ramayapatnam-to-Tettu connection under the Gati-Shakti Multi-Modal Cargo Terminal Policy and that work on the serving-station yard was at an advanced stage. It did not provide a completion date or establish completed rail access and cargo-evacuation readiness.
The Ministry of Ports, Shipping and Waterways listed Ramayapatnam among four Andhra Pradesh ports under construction. This is a portfolio-status confirmation, not a package percentage, completion date or operating approval.
A Lok Sabha answer recorded the INR 4,929.39 crore port under implementation at 52.95% and described 34.04 MMTPA Phase I capacity. The percentage predates the DEME award by more than a year and cannot be used as dredging-package progress.
North-breakwater, navigation-aid and VTMS funding remained proposals
Parliament listed INR 409.05 crore for the north breakwater, INR 12.59 crore for fire-fighting and navigational aids, and INR 34.35 crore for VTMS among Andhra Pradesh proposals. The ministry requested restructuring and alternative funding exploration; the list is not award or completion evidence.
Andhra Pradesh recorded initiation of the greenfield port
The SPSR Nellore district event register records initiation of the greenfield Ramayapatnam Port. It establishes the start boundary for the wider programme, not the later DEME package or completion of any marine element.
The Ministry of Environment, Forest and Climate Change granted environmental and coastal-regulation-zone clearance for Phase I subject to project-specific and standard conditions. Clearance enabled the programme but did not award works, approve every later design change or prove construction acceptance.