Project record

Port of Tanjung Pelepas Berth Zero

Port of Tanjung Pelepas, MMC Engineering and Antara Koh representatives signing the Berth Zero development contract

MMC Corporation Berhad; exact 24 October 2025 Berth Zero contract-signing event

Port of Tanjung Pelepas is developing Berth Zero as a 360-metre marine and terminal expansion. PTP awarded the package to an MMC Engineering-Antara Koh joint venture in October 2025. The scope includes dredging, reclamation, berth construction and an eRTG-ready yard. A January 2026 Marine Department circular names pontoons, crane barges, barges and tugs working on Package 1 and Package 2, confirming mobilisation beyond the award announcement.

Project signal

Construction in Malaysia

Current status Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028 Source confidence Confirmed

Location

Malaysia / Asia Pacific

Segment

Deep-water ports and container terminals

Status

Malaysia Marine Department notices documented Package 1 and Package 2 work vessels on site from January 2026; PTP is delivering a 360-metre berth, dredging, reclamation, yard works and four quay cranes toward commissioning by 2028 / Confirmed

Last checked

1 August 2026

Coverage

Related sectors

Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
Pelabuhan Tanjung Pelepas Sdn Bhd, owned by MMC Group (70%) and APM Terminals (30%)
Delivery parties
MMC Engineering Sdn Bhd-Antara Koh (M) Sdn Bhd joint venture - dredging, reclamation, 360-metre berth and associated yard development, Antara Koh - marine-piling and marine-structures specialist within the civil joint venture, Libroy 128 pontoon, Antara Koh 388 and 228 crane barges, Terang 18 barge, and Antara Koh AB 6 and AB28 tugs - working vessels listed by the Marine Department; vessel listing does not by itself identify every owner or subcontract, Four quay cranes - planned for commissioning by 2028; supplier not identified in the reviewed Berth Zero award, No reviewed primary source allocates the full dredging fleet, reclamation fill chain, ground-improvement package, eRTGs, power systems or terminal software to named downstream suppliers
Contract route
PTP awarded the Berth Zero development to the MMC Engineering-Antara Koh joint venture on 24 October 2025. Malaysia Marine Department circular 01/2026 then notified active Package 1 and Package 2 works and listed the working fleet from 10 January to 29 March 2026. The package is part of PTP's operator-funded capacity programme rather than a separate public concession.
Execution window
The civil award was announced in October 2025. Marine work vessels were active from January 2026 under Package 1 and Package 2 notices. PTP expects the four quay cranes to be commissioned by 2028 and targets approximately 16 million TEU annual capacity by 2029 across the wider port programme.
Works package
Carry out dredging and reclamation, construct a 360-metre new berth, prepare the adjoining container yard for electric RTGs and integrate four new quay cranes. The berth adds quay capacity to a terminal that handled 14 million TEU in 2025; the full 16 million TEU target depends on this and other equipment and productivity investments.
Marine interfaces
Dredging, reclamation, piling, berth deck, crane rails, yard formation, drainage, power and equipment delivery must be sequenced around an operating transshipment hub. The Marine Department's vessel list confirms in-water mobilisation but does not prove dredging quantities, berth geometry or package completion.
Commercial evidence boundary
The client, civil joint venture and active working fleet are visible, providing a stronger chain than an award-only record. Contract value, dredging quantity, reclamation source, foundation design, downstream subcontractors, four-crane supplier and package-level acceptance dates are not public in the reviewed primary disclosures.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

PTP linked Berth Zero to its 16 million TEU capacity target

The operator confirmed the 360-metre berth and four cranes remain part of the active expansion programme toward a 2029 capacity target.

Source

Marine Department circular confirmed working vessels

The Package 1 and Package 2 notice listed a pontoon, two crane barges, another barge and two tugs, moving the evidence from award to marine mobilisation.

Source

The Berth Zero civil package was awarded

PTP selected the MMC Engineering-Antara Koh joint venture for dredging, reclamation, berth and yard works, with four quay cranes planned by 2028.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Dredging quantity, disposal or reuse route and hydrographic acceptance
  • Reclamation fill source, ground improvement and settlement monitoring
  • Pile, quay deck and crane-rail construction milestones
  • Package 1 and Package 2 subcontract and fleet allocation
  • Four Berth Zero quay-crane supplier and delivery schedule
  • eRTG-ready yard power, drainage and pavement acceptance
  • 2028 berth and crane commissioning and 2029 capacity release

Reporting status

Construction, confirmed confidence

Last checked 1 August 2026 across 5 cited sources. The dated timeline above carries the project events.

Last checked 1 August 2026 Cited sources 5