Port Delivery
Berth Zero moves from award to a named marine fleet
Malaysia Marine Department; exact 10 January 2026 Berth Zero navigation and working-vessel notice
Berth Zero has crossed an evidence threshold that many project trackers miss. PTP's October 2025 award identified the MMC Engineering-Antara Koh joint venture and the dredging, reclamation, berth and yard scope. Malaysia Marine Department's January 2026 circular then listed the pontoons, crane barges, barge and tugs working on Package 1 and Package 2.
The work-vessel notice confirms physical mobilisation
Port Circular 01/2026 is the controlling mobilisation evidence and lists the work window and vessels. MMC and PTP control the award and scope. The circular does not allocate every vessel owner, subcontractor, dredging quantity or acceptance result, and current fleet-wide crane orders are kept outside the Berth Zero chain.
Marine mobilisation precedes full supplier allocation
A contract award alone cannot establish that marine work started. The navigation notice puts named vessels inside a defined work window at Tanjung Pelepas, creating a verifiable construction signal. It also shows where evidence stops: the notice does not provide dredging quantities, production, subcontract values or package acceptance.
Evidence conclusion
Named working vessels define the mobilisation boundary
The MMC Engineering-Antara Koh joint venture is the confirmed civil delivery party. The four Berth Zero quay cranes remain supplier-unallocated in the project-specific record. Separate 2026 PTP announcements concerning Sany and ZPMC fleet orders should not be attached to Berth Zero unless the operator names that berth directly. Remaining disclosures are quantities, foundations, fill source and crane allocation.
Outstanding evidence
- Package 1 and Package 2 scope split
- Dredging quantity, plant ownership and hydrographic acceptance
- Reclamation source, ground treatment and settlement monitoring
- Quay piles, deck and crane-rail milestones
- Four project-specific quay-crane supplier and commissioning dates
- 2028 berth release and 2029 capacity contribution
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Sources used 4
- Port Circular 01/2026: Berth Zero Package 1 and Package 2 Malaysia Marine Department, 10 January 2026
- Port of Tanjung Pelepas develops Berth Zero MMC Corporation Berhad, 24 October 2025
- PTP Berth Zero development announcement Port of Tanjung Pelepas, 24 October 2025
- PTP targets 16 million TEU annual capacity Port of Tanjung Pelepas, 15 June 2026