Damietta Alliance Container Terminals began commercial operations on 14 February 2026 with the first Hapag-Lloyd call. The 93-hectare terminal has 1,670 metres of quay at 18 metres water depth. Its delivery split matters: Damietta Port Authority provided the quay walls, excavation, access-channel and basin dredging, while the concession company financed and built the terminal superstructure and equipment.
Project signal
Commissioning in Egypt
Current statusCommercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacitySource confidenceConfirmed
Location
Egypt / Africa
Segment
Deep-water ports and container terminals
Status
Commercial operations began on 14 February 2026; the terminal is moving through its 2026 ramp-up and the 3.3 million TEU figure remains final design capacity / Confirmed
Last checked
20 July 2026
Coverage
Related sectors
Deep-water ports and container terminals is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
Related subjects
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract scope and delivery roles
Client / authority
Damietta Port Authority; Damietta Alliance Container Terminals S.A.E.
Delivery parties
Arab Contractors and Archirodon for the port-authority quay and dredging works identified in the stakeholder plan, Damietta Alliance Container Terminals for terminal development and operation under the 30-year concession
Contract route
The 30-year build-operate-transfer concession was signed on 18 May 2022. Damietta Port Authority retained responsibility for land excavation and foundations, quay walls, dredging of the access channel and basin, utilities, access roads and rail up to the terminal boundary. The concession company raised a USD 455 million lender package for the separate superstructure, pavement, electrical systems, buildings and terminal equipment.
Execution window
The lender disclosure described the public quay and dredging works as the platform to be handed to the concession company for terminal construction. Commercial operations started on 14 February 2026. Hapag-Lloyd describes full operations as a later 2026 step and the 3.3 million TEU capacity as available after the final construction phase, so neither should be recorded as achieved output yet.
Works package
The U-shaped terminal occupies about 93 hectares and provides 1,670 metres of quay at 18 metres water depth. The opening configuration includes 12 fully electric ship-to-shore cranes, 40 hybrid rubber-tyred gantry cranes and six rail lanes, of which two were operational at launch. The current terminal page lists a final equipment plan of up to 16 ship-to-shore cranes and 55 yard cranes.
Marine interfaces
The marine platform joins the dredged approach and enclosed basin to two long quay faces, berth pockets, quay structures, fenders, mooring, pavement, crane rails, shore power, drainage and terminal controls. Because the port authority and concession company delivered opposite sides of that boundary, accepted depth, quay handover, equipment commissioning and safe vessel handling cannot be inferred from a single contract or financing milestone.
Commercial evidence boundary
The first call confirms that at least one service and berth sequence entered commercial use. Public records available through July 2026 do not establish final crane deployment, full rail availability, sustained berth productivity, annual throughput or maintenance-dredging demand. Those operating measures now matter more than the historic construction headline.
Project timeline
Material developments
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
The first Hapag-Lloyd call moved the terminal into live service with 12 ship-to-shore cranes, 40 yard cranes and two operational rail lanes. Full operations and final capacity remain later measures.
The international lender group signed a USD 455 million package
The package financed the concession company's terminal superstructure. It did not finance the port authority's separate quay-wall, excavation and dredging scope.