Ports

Damietta CT2 is handling ships; its 3.3m TEU rating still sits ahead of the operating record

Published 20 July 2026 Editorial responsibility IMWO Region Africa Confidence Confirmed
Egyptian flag, harbour tug and Damietta Alliance ship-to-shore cranes beside an active berth at the new terminal

Damietta Alliance Container Terminals

Damietta Alliance Container Terminals started commercial operations on 14 February 2026. The opening configuration has 1,670 metres of quay at 18 metres depth, 12 ship-to-shore cranes, 40 yard cranes and two operational rail lanes. The 3.3 million TEU figure remains the terminal's capacity after the final construction phase, not measured throughput.

What changed

Damietta Alliance and Hapag-Lloyd confirm the 14 February commercial opening, first call, terminal dimensions and launch equipment. AIIB and the project non-technical summary define Damietta Port Authority's associated quay, excavation and dredging works. The lender group records the separate USD 455 million financing for the concession company's superstructure. Hapag-Lloyd describes full operations and final 3.3 million TEU capacity as later outcomes in 2026.

Why it matters

Damietta CT2 was delivered across a clean but easily missed boundary. The port authority carried the quay walls, excavation and access-channel and basin dredging. The concession company financed the pavement, power, buildings, rail and handling equipment. The first commercial call proves those packages worked together at initial service level; it does not erase their separate owners, acceptance records or maintenance obligations.

Decision read

Commercial opening is confirmed; full output is not

The opening establishes usable marine access and an initial terminal operating chain. Repeat calls, berth productivity, the remaining rail lanes, final crane deployment, accepted post-opening depths and maintenance demand will show how far the ramp-up has progressed. The 3.3 million TEU figure remains design capacity unless the terminal reports sustained output at that level.

Next watchpoints

  • Repeat scheduled calls after the February launch
  • Formal full-operations announcement in 2026
  • Final ship-to-shore and yard-crane deployment
  • Commissioning of the remaining rail lanes
  • Published throughput and berth-productivity data
  • Post-opening hydrographic acceptance and navigation notices
  • First maintenance-dredging scope and material route
  • Warranty and handover close-out across the quay-to-terminal boundary

Knowledge context

Related knowledge topics

Continue through the topic collections to compare this record with related projects, evidence guides, briefs, articles, reports, and performance records.

Sources used 7

Corrections and methodology

Facts are dated to the source record above. IMWO updates the brief when procurement, award, delivery, or scope evidence materially changes.

Review methodology Open intelligence archive Submit a correction