Morocco's Ministry of Equipment and Water is building Dakhla Atlantic Port under contract 03/DPDPM/2021. SOMAGEC's contract sheet identifies a 50/50 SGTM-SOMAGEC SUD group, an 84-month October 2021 to September 2028 period and a MAD 12.401 billion tax-inclusive value. The works include a 6.75 km protection breakwater, 1.33 km marine access viaduct, 2.958 km of quays at three design levels, 68 hectares of reclaimed platforms and 279,000 m3 of dredging. Ministry-attributed reporting put overall progress above 60% in June 2026. Specialist-subcontract, equipment and operating appointments remain only partly disclosed.
Morocco / Africa
Port infrastructure
Construction reported above 60% in June 2026; marine completion, equipment and operating awards remain open / Confirmed
14 August 2026
Coverage
Port infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe update reported 85.4% progress on the marine viaduct and 44% on fill works, showing that headline progress does not mean all marine packages are equally advanced.
SourceMinistry-attributed reporting also recorded 48.63% financial progress, launched dredging, quay-element prefabrication and filling, and approval of a SOCOTEC surveillance contract. It did not establish completion of those packages.
SourceThe inspection supplied the first reviewed owner checkpoint used in this record and confirmed that the large civil and marine programme remained in construction.
SourceThe contract fixed the SGTM-SOMAGEC SUD joint venture, equal participation, 84-month duration, precise value and principal marine quantities.
SourceEvidence gap