Project record

Hammond Cove Marina reconstruction

Participation
Not assessed
Project facts checked

New York City's 22 January 2026 award notice names Empire Construction and Property Management Group at USD 4,583,648 for X310-117M; the city hazard plan identifies bulkhead, dock and electrical reconstruction, but no cited record establishes contract signing, notice to proceed, mobilisation or completion

Project sources

New York City Parks published a USD 4,583,648 competitive-sealed-bid award to Empire Construction and Property Management Group for X310-117M Hammond Cove Marina Reconstruction in the Bronx. The award appeared in The City Record on 22 January 2026 under PIN 84623B0106001. New York City's hazard-mitigation action register defines the project as reconstruction of Hurricane Sandy-damaged bulkhead, dock and electrical elements. The archived solicitation identifies construction services and a USD 3 million to USD 5 million estimate but places drawings, specifications and quantities inside PASSPort. A separate NYCEDC-led entrance-channel dredging project was announced in 2022 and is not assigned to this construction award.

Hammond Cove Marina docks and boats behind New York City project partners holding a tide gauge

NYCEDC; Hammond Cove entrance-channel dredging event, 22 December 2022. Site context, not X310-117M construction progress

Location

United States / Americas

Segment

Marinas, pontoons and berthing infrastructure

Phase

Award / Confirmed

Last checked

15 August 2026

Coverage

Related sectors

Marinas, pontoons and berthing infrastructure is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.

Subject index

Related subjects

These subject pages bring together related projects, technical articles, reports, and evidence methods.

Project anatomy

Contract scope and delivery roles

Client / authority
New York City Department of Parks and Recreation - Capital Program Management
Delivery parties
Empire Construction and Property Management Group - published construction award vendor under PIN 84623B0106001, Design, construction supervision and other owner-side services - not assigned to a named external consultant in the cited records, Marine demolition, piling, dock fabrication, electrical and other lower tiers - not named in the cited public records
Contract route
NYC Parks issued competitive sealed bid 84623B0106 for X310-117M in 2024. The archived solicitation stated a USD 3 million to USD 5 million estimate and required bid documents to be retrieved through PASSPort. The 22 January 2026 City Record award notice uses PIN 84623B0106001 and reports Empire Construction and Property Management Group at USD 4,583,648. The publication date is not treated as the contract-signing, notice-to-proceed or mobilisation date.
Execution window
The February 2026 OMB commitment plan schedules USD 73,000 of design during construction and USD 684,000 of in-house construction supervision for June 2026. These are planned owner-side commitments, not proof that construction started or that those amounts were spent. The executed construction period, notice to proceed, field mobilisation, substantial completion and operating release remain unpublished.
Works package
New York City's hazard-mitigation action register identifies reconstruction of Hurricane Sandy-damaged bulkhead, dock and electrical elements at the marina. The public record does not expose drawings, specifications, quantities, dock geometry, pile requirements, demolition limits, electrical capacity or the allocation between marine and landside work. The 2022 entrance-channel dredging was a separate NYCEDC-led project and is not included in X310-117M on the evidence reviewed.
Marine interfaces
Hammond Cove is NYC Parks' only marina in the Bronx and a city-owned waterfront facility. Bulkhead and dock reconstruction creates direct tidal-access, temporary-berthing, marina-operation and waterfront-resilience interfaces. The public record does not define navigational closures, temporary dockage, design water level, pile or bulkhead geometry, marine plant, environmental controls or the operating-concession interface.
Commercial evidence boundary
USD 4,583,648 is the amount printed in the City Record award notice. It sits within the solicitation's USD 3 million to USD 5 million estimate range but is not evidence of expenditure, paid value, final account or package-level allocation. No public amount can be assigned to marine works, landside works, owner supervision, design support, contingencies, amendments or subcontractors.

Contract and delivery chain

Work packages and named roles

Published scope, named parties and supporting evidence for each workstream.

Construction award

X310-117M Hammond Cove Marina Reconstruction

Named party
Empire Construction and Property Management Group
Evidence status
Confirmed
Source position
The 22 January 2026 City Record award notice reports competitive sealed bid PIN 84623B0106001 and a USD 4,583,648 amount to the named vendor. Source
Solicitation

84623B0106 construction services

Named party
NYC Parks - Capital Program Management
Evidence status
Confirmed
Source position
The archived solicitation records competitive sealed bids, the USD 3 million to USD 5 million estimate range and the requirement to retrieve bid documents through PASSPort. Source
Owner-side delivery support

Design during construction and in-house supervision

Named party
New York City Department of Parks and Recreation
Evidence status
Confirmed
Source position
The February 2026 OMB plan lists USD 73,000 for design during construction and USD 684,000 for in-house construction supervision, both planned for June 2026; the plan is not progress or expenditure evidence. Source
Asset scope

Sandy-damaged bulkhead, dock and electrical reconstruction

Named party
NYC Parks and Empire Construction and Property Management Group
Evidence status
Confirmed
Source position
New York City's hazard-mitigation action register names reconstruction of Sandy-damaged bulkhead, dock and electrical elements; drawings, quantities and detailed work allocation remain unpublished. Source
Delivery and close-out

Mobilisation, construction, acceptance and return to service

Named party
NYC Parks and Empire Construction and Property Management Group
Evidence status
Not evidenced
Source position
No cited owner source confirms contract signing, notice to proceed, mobilisation, installed work, substantial completion, final account or operating release.

Project timeline

Material developments

Dated events that changed scope, counterparties, delivery, commissioning or operating status.

Open this project in the Change Log

NYC published the USD 4.58 million construction award

The award notice names Empire Construction and Property Management Group and fixes the public contract amount, while leaving signing and delivery status unverified.

Source

City hazard plan identified the reconstruction assets

The official action register confirms Sandy-damaged bulkhead, dock and electrical reconstruction while leaving drawings, quantities and field status unresolved.

Source

NYC Parks extended the competitive solicitation

The archived notice retained competitive sealed bidding and a USD 3 million to USD 5 million estimate; detailed bid documents remained in PASSPort.

Source

Evidence gap

What remains unverified

Outstanding evidence

  • Executed contract and notice-to-proceed date
  • PASSPort drawings, specifications, quantities and design criteria
  • Bulkhead, dock and electrical work breakdown and temporary marina arrangements
  • Named designer, construction manager and project-specific lower tiers
  • Marine access, environmental controls and operational-closure plan
  • Field mobilisation and dated construction progress
  • Contract amendments, payments and final account
  • Substantial completion, owner acceptance and return to service

Reporting status

Project phase
Award
Evidence confidence
Confirmed
Last checked
15 August 2026
Cited sources
7

Sources and related records

Project changes Methodology Email a correction Project tracker

Project sources 7