Location
United Kingdom / Europe
Project record
Find a Tender records an active award to ZPMC for four STS cranes at GBP 43.594 million excluding VAT; actual contract signature, manufacture, shipment, commissioning and acceptance remain unconfirmed
The Felixstowe Dock and Railway Company awarded TC01361 to Shanghai Zhenhua Heavy Industries Co., Ltd. for four ship-to-shore quay cranes. Notice 060700-2025 reports an active GBP 43,594,074 excluding-VAT award and GBP 52,312,888 including VAT, against a GBP 52 million excluding-VAT tender estimate. The planned 3 October 2025 signature and 1 October 2027 end remain scheduling fields. Wheel-load, outreach, lift-height and capacity requirements govern the equipment design; signed terms and physical delivery remain unconfirmed.
United Kingdom / Europe
Container-terminal handling equipment
Award / Confirmed
14 October 2026
Coverage
Container-terminal handling equipment is the primary work classification. Related sectors connect this record to adjacent marine delivery and market coverage.
Subject index
These subject pages bring together related projects, technical articles, reports, and evidence methods.
Project anatomy
Contract and delivery chain
Published scope, named parties and supporting evidence for each workstream.
Project timeline
Dated events that changed scope, counterparties, delivery, commissioning or operating status.
Open this project in the Change LogThe notice names ZPMC as the active award supplier at GBP 43.594 million excluding VAT. The scheduled signature milestone and planned period leave contract execution and delivery unconfirmed.
SourceThe buyer updated the technical specification and form of tender, extended submission to 5 September and confirmed electronic submissions.
SourceThe initial tender established four cranes, a GBP 52 million excluding-VAT estimate, strict wheel-load constraints and a two-stage technical and commercial assessment.
SourceEvidence gap